18605 W LEMAY ST 91335

Certificate Information: 18605 W LEMAY ST 91335

Application / Permit
24014-20000-02145
Plan Check / Job No.
B24VN07034
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. Convert (E) 368 sf Detached Garage into ADU with 727 sf addition per LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 9/30/2024
Issuing Office
Current Status
Issued on 9/30/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/20/2024 APPLICANT
Assigned to Plan Check Engineer 5/24/2024 AMY GUEVARRA
Corrections Issued 5/25/2024 AMY GUEVARRA
Applicant returned to address corrections 9/26/2024 AMY GUEVARRA
Plan Check Approved 9/30/2024 AMY GUEVARRA
Issued 9/30/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/28/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 5/28/2024 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 5/28/2024 CARLOS RAMIREZ
Sewer availability Cleared 5/28/2024 CARLOS RAMIREZ
ZI Cleared 5/28/2024 DORIAN AGUILAR
Construction within easement Cleared 9/25/2024 RIDWAN HARDY

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/5/2025 Partial Inspection ARUTYUN MADATYAN
PLUMBING-Rough 2/11/2025 Partial Approval ARUTYUN MADATYAN
Sewer 2/11/2025 Approved ARUTYUN MADATYAN
Deputy Drilled-In Anchors 2/25/2025 Conditional Approval HENRY KIM
Footing/Foundation/Slab 2/25/2025 Corrections Issued HENRY KIM
Excavation/Setback/Form/Re-Bar 3/5/2025 Not Ready for Inspection ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 4/8/2025 Corrections Issued ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 4/14/2025 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 4/29/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Rough 4/29/2025 Approved ARUTYUN MADATYAN
Green Building Rough 4/29/2025 Approved ARUTYUN MADATYAN
HVAC-Rough 4/29/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 4/29/2025 Corrections Issued ARUTYUN MADATYAN
PLUMBING-Rough 4/29/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 5/2/2025 Partial Approval ARUTYUN MADATYAN
Shower Pan 5/2/2025 Approved ARUTYUN MADATYAN
Insulation 5/8/2025 Conditional Approval ARUTYUN MADATYAN
Drywall Nailing 5/14/2025 Approved ARUTYUN MADATYAN
Drywall Nailing 5/15/2025 No Access for Inspection TROY SANDERS
Final 4/13/2026 No Access for Inspection ARUTYUN MADATYAN
Footing/Foundation/Slab 4/13/2026 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 4/13/2026 SGSOV Not Ready ARUTYUN MADATYAN
Service/Power Release 4/13/2026 Not Ready for Inspection ARUTYUN MADATYAN
Smoke Detectors 4/13/2026 Not Ready for Inspection ARUTYUN MADATYAN
Final 4/24/2026 Not Ready for Inspection JUAN ALVARADO
SGSOV-Seismic Gas S/O Valve 4/24/2026 SGSOV Not Ready JUAN ALVARADO
Service/Power Release 4/24/2026 Not Ready for Inspection JUAN ALVARADO
Smoke Detectors 4/24/2026 Not Ready for Inspection JUAN ALVARADO
SGSOV-Seismic Gas S/O Valve 5/1/2026 SGSOV Not Ready ARUTYUN MADATYAN
Final 5/8/2026 Corrections Issued ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 5/8/2026 SGSOV Not Ready ARUTYUN MADATYAN
Service/Power Release 5/8/2026 Not Ready for Inspection ARUTYUN MADATYAN
Smoke Detectors 5/8/2026 Approved ARUTYUN MADATYAN