15015 W COPPER ST 91345
Certificate Information: 15015 W COPPER ST 91345
- Application / Permit
- 24014-20000-02138
- Plan Check / Job No.
- B24VN06999
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED IRREGULAR SHAPED ADDITION TO (E) SINGLE FAMILY DWELLING PER ENGINEERING. NFPA-13D FIRE SPRINKLERES THRU-OUT
- Permit Issued
- Issued on 11/6/2024
- Issuing Office
- Current Status
- CofO Issued on 8/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/28/2024 | ALFRED RAMIREZ |
| Corrections Issued | 5/29/2024 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 10/9/2024 | MOHAMMAD ESMAILI |
| Plan Check Approved | 10/23/2024 | SARKIS HARABEDIAN |
| Issued | 11/6/2024 | APPLICANT |
| CofO in Progress | 8/4/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 8/14/2025 | RUBEN SALAS |
| CofO Issued | 8/14/2025 | RUBEN SALAS |
| Permit Finaled | 8/14/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/3/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 6/6/2024 | BIAINA HARITUNIAN |
| Tract Map conditions | Cleared | 6/7/2024 | STEVEN WECHSLER |
| Construction near power lines | Cleared | 10/7/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yu,, Jennifer Arianna; Lic. No.: C79156 | 3828 EARLE AVE ROSEMEAD, CA 91770 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/27/2024 | Partial Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 1/7/2025 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 1/7/2025 | Approved | JACK KARGODORIAN |
| Sewer | 1/7/2025 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2025 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/24/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 2/24/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 2/24/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 2/24/2025 | Approved | JENNIFER RABUCHIN |
| MERV13>=Rough | 2/24/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/24/2025 | Approved | JENNIFER RABUCHIN |
| Insulation | 3/7/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/13/2025 | Approved | DAVID ANDERSON |
| Drywall Nailing | 3/13/2025 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 3/13/2025 | Partial Approval | DAVID ANDERSON |
| Final | 7/7/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 7/7/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 7/7/2025 | Corrections Issued | JENNIFER RABUCHIN |
| MERV13>=Final | 7/7/2025 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 7/7/2025 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 7/7/2025 | Approved | JENNIFER RABUCHIN |
| Final | 7/25/2025 | Corrections Issued | JENNIFER RABUCHIN |
| MERV13>=Final | 7/25/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 8/4/2025 | Approved | JENNIFER RABUCHIN |
| Final | 8/4/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 8/4/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 8/4/2025 | Approved | JENNIFER RABUCHIN |