7028 N STANSBURY AVE 91405

Certificate Information: 7028 N STANSBURY AVE 91405

Application / Permit
24014-20000-02133
Plan Check / Job No.
B24VN06975
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE AND NEW ADDITION TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 10/21/2024
Issuing Office
Current Status
CofO Issued on 2/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/17/2024 APPLICANT
Assigned to Plan Check Engineer 5/23/2024 JESSE ARELLANO
Corrections Issued 5/24/2024 JESSE ARELLANO
Building Plans Picked Up 5/29/2024 APPLICANT
Applicant returned to address corrections 10/1/2024 MIROOSH KHACHATOORIAN
Issued 10/21/2024 APPLICANT
CofO in Progress 2/21/2025 RYAN SALAZAR
Permit Finaled 2/27/2025 RUBEN SALAS
CofO Issued 2/27/2025 RUBEN SALAS
Permit Finaled 2/27/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/28/2024 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 5/28/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 5/28/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 5/30/2024 LEE GUILBEAUX
Sewer availability Cleared 5/30/2024 LEE GUILBEAUX
Construction near power lines Cleared 9/25/2024 RIDWAN HARDY
Permit Cleared 10/21/2024 LEE GUILBEAUX
Trees in Parkway Cleared 10/21/2024 MIGUEL ORNELAS

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/8/2024 Partial Approval RYAN SALAZAR
Deputy Drilled-In Anchors 11/13/2024 Conditional Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 11/13/2024 Approved RYAN SALAZAR
Footing/Foundation/Slab 11/13/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 11/27/2024 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 12/4/2024 Approved RYAN SALAZAR
Wood Frame 12/4/2024 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 12/12/2024 Approved RYAN SALAZAR
HVAC-Rough 12/12/2024 Approved RYAN SALAZAR
PLUMBING-Rough 12/12/2024 Approved RYAN SALAZAR
Insulation 12/17/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 12/17/2024 Partial Approval RYAN SALAZAR
Shower Pan 12/17/2024 Approved RYAN SALAZAR
Drywall Nailing 12/26/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 12/26/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 2/14/2025 Approved RYAN SALAZAR
Green Building Rough 2/14/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 2/14/2025 SGSOV Not Ready RYAN SALAZAR
Final 2/19/2025 Corrections Issued RYAN SALAZAR
Green Building Final 2/19/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 2/19/2025 SGSOV Approved RYAN SALAZAR
Smoke Detectors 2/19/2025 Approved RYAN SALAZAR
Final 2/24/2025 OK to Issue CofO RYAN SALAZAR
Service/Power Release 2/24/2025 Approved RYAN SALAZAR