5450 N NAGLE AVE 91401
Certificate Information: 5450 N NAGLE AVE 91401
- Application / Permit
- 24014-20000-02121
- Plan Check / Job No.
- B24VN06942
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 8'-0" x 16'-2" REAR ADDITION TO THE (E) SINGLE FAMILY DWELLING. TO ADD A MASTER BEDROOM AND CLOSET TO THE MASTER BEDROOM.
- Permit Issued
- Issued on 5/20/2024
- Issuing Office
- Current Status
- CofO Issued on 9/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/17/2024 | GIOVANNY CHAVEZ |
| Corrections Issued | 5/17/2024 | GIOVANNY CHAVEZ |
| Issued | 5/20/2024 | APPLICANT |
| CofO in Progress | 8/29/2024 | RYAN SALAZAR |
| Permit Finaled | 9/12/2024 | DANIEL ORRANTE |
| CofO Issued | 9/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 5/20/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Service/Power Release | 6/12/2024 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2024 | Approved | RYAN SALAZAR |
| Rough-Elec/Plmb/HVAC | 7/5/2024 | Approved | RYAN SALAZAR |
| Insulation | 7/11/2024 | Approved | RYAN SALAZAR |
| Shower Pan | 7/11/2024 | Approved | RYAN SALAZAR |
| Drywall Nailing | 7/16/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 7/23/2024 | Approved | LOUIS ESCOTO |
| BUILDING-Rough-Frame | 8/28/2024 | Approved | RYAN SALAZAR |
| Final | 8/28/2024 | OK to Issue CofO | RYAN SALAZAR |
| Footing/Foundation/Slab | 8/28/2024 | Approved | RYAN SALAZAR |
| Green Building Final | 8/28/2024 | Approved | RYAN SALAZAR |
| Green Building Rough | 8/28/2024 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 8/28/2024 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 8/28/2024 | Approved | RYAN SALAZAR |