CONVERT (E) 19' X 20' DETACHED GARAGE AND (N) 23'-2" X 38'-5" ADDITION TO (N) ACCESSORY DWELLING UNIT (1187.55 SF) PER LAMC 12.22.A.33(c) AND (d). WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 10/7/2024
Issuing Office
Current Status
CofO Issued on 9/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/17/2024 APPLICANT
Assigned to Plan Check Engineer 5/24/2024 MADISON ODELL
Corrections Issued 5/28/2024 MADISON ODELL
Applicant returned to address corrections 6/20/2024 MADISON ODELL
Applicant returned to address corrections 6/22/2024 MADISON ODELL
Plan Check Approved 10/3/2024 GIOVANNY CHAVEZ
Issued 10/7/2024 APPLICANT
CofO in Progress 9/9/2025 JENNIFER RABUCHIN
Permit Finaled 9/10/2025 RUBEN SALAS
Permit Finaled 9/10/2025 RUBEN SALAS
CofO Issued 9/10/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/7/2024 TAL SHEMEN
Roof/Waste drainage to street Cleared 6/7/2024 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 6/18/2024 TAL SHEMEN
Sewer availability Cleared 6/18/2024 TAL SHEMEN
Construction near power lines Cleared 9/30/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/24/2024 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 10/24/2024 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 11/19/2024 Partial Approval JENNIFER RABUCHIN
Underground Mechanical 11/19/2024 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/22/2024 Partial Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 11/22/2024 Partial Approval MICHEL ABAJAN
Green Building Rough 11/22/2024 Partial Inspection MICHEL ABAJAN
ELECTRICAL-Rough 1/29/2025 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 1/29/2025 Conditional Approval JENNIFER RABUCHIN
HVAC-Rough 1/29/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 1/29/2025 Approved JENNIFER RABUCHIN
Deputy Wood Construction 1/31/2025 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 2/7/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 2/7/2025 Approved JENNIFER RABUCHIN
Green Building Rough 2/7/2025 Approved JENNIFER RABUCHIN
HVAC-Rough 2/7/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 2/7/2025 Partial Approval JENNIFER RABUCHIN
Insulation 2/26/2025 Approved JENNIFER RABUCHIN
PLUMBING-Rough 2/26/2025 Corrections Issued JENNIFER RABUCHIN
Drywall Nailing 3/5/2025 Approved JENNIFER RABUCHIN
Shower Pan 3/5/2025 Approved JENNIFER RABUCHIN
Final 7/29/2025 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 7/29/2025 Approved JENNIFER RABUCHIN
Green Building Final 7/29/2025 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 7/29/2025 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 7/29/2025 Approved JENNIFER RABUCHIN
Final 8/5/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Final 8/5/2025 Approved JENNIFER RABUCHIN
Service/Power Release 8/7/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 9/5/2025 Approved JENNIFER RABUCHIN
Final 9/5/2025 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 9/5/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 9/5/2025 Approved JENNIFER RABUCHIN
Service/Power Release 9/5/2025 Approved JENNIFER RABUCHIN