8701-8703 N CRANFORD AVE 91352
Certificate Information: 8701-8703 N CRANFORD AVE 91352
- Application / Permit
- 24014-20000-02089
- Plan Check / Job No.
- B24VN06867
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 22' X 43' IRREGULAR SHAPED ADDITION AND MAJOR REMODEL TO (E) SFD. ADD 20' X 21'-0.5" PATIO COVER AT REAR. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/6/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2024 | RAPHAEL ROSAS |
| Corrections Issued | 6/6/2024 | RAPHAEL ROSAS |
| Quality Review Completed | 6/14/2024 | STEVEN KIM |
| Building Plans Picked Up | 6/14/2024 | APPLICANT |
| Applicant returned to address corrections | 8/7/2024 | RAPHAEL ROSAS |
| Plan Check Approved | 9/6/2024 | RAPHAEL ROSAS |
| Issued | 9/6/2024 | APPLICANT |
| CofO in Progress | 5/28/2025 | NICHOLAS TROWBRIDGE |
| Permit Finaled | 9/26/2025 | RUBEN SALAS |
| CofO Issued | 9/26/2025 | RUBEN SALAS |
| Permit Finaled | 9/26/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/18/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 6/18/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 6/18/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/20/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/9/2024 | Approved | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 9/13/2024 | Conditional Approval | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 9/24/2024 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 9/24/2024 | Corrections Issued | MATTHEW NELSON |
| METHANE-Barrier | 9/24/2024 | Approved | MATTHEW NELSON |
| METHANE-Subgrade | 9/24/2024 | Approved | MATTHEW NELSON |
| Piling/Pier/Caisson | 9/24/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 10/1/2024 | Approved | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 11/14/2024 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2024 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 11/14/2024 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 12/9/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 12/9/2024 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/18/2024 | Approved | MATTHEW NELSON |
| Green Building Rough | 12/18/2024 | Approved | MATTHEW NELSON |
| HVAC-Rough | 12/18/2024 | Approved | MATTHEW NELSON |
| METHANE-Rough | 12/18/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 12/24/2024 | Partial Approval | MATTHEW NELSON |
| Insulation | 12/30/2024 | Approved | MATTHEW NELSON |
| Drywall Nailing | 1/9/2025 | Approved | MATTHEW NELSON |
| Shower Pan | 1/9/2025 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 2/3/2025 | Approved | MATTHEW NELSON |
| Shower Pan | 2/3/2025 | Approved | MATTHEW NELSON |
| Underground Mechanical | 3/4/2025 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 5/2/2025 | Approved | NICHOLAS TROWBRIDGE |
| Final | 5/2/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Green Building Final | 5/2/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| HVAC-Final | 5/2/2025 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Final | 5/2/2025 | Approved | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 5/2/2025 | SGSOV Not Ready | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 5/2/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Final | 5/14/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Final | 5/14/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Green Building Final | 5/14/2025 | Approved | NICHOLAS TROWBRIDGE |
| HVAC-Final | 5/14/2025 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Final | 5/14/2025 | Approved | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 5/14/2025 | SGSOV Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Final | 5/27/2025 | Approved | NICHOLAS TROWBRIDGE |
| Final | 5/27/2025 | OK to Issue CofO | NICHOLAS TROWBRIDGE |
| HVAC-Final | 5/27/2025 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Final | 5/27/2025 | Approved | NICHOLAS TROWBRIDGE |
| Service/Power Release | 5/27/2025 | Approved | NICHOLAS TROWBRIDGE |