8341-8343 N QUARTZ AVE 91306

Certificate Information: 8341-8343 N QUARTZ AVE 91306

Application / Permit
24014-20000-02070
Plan Check / Job No.
B24VN06797
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Convert (E) attached garage with addition to (N) attached ADU per city ordinance.
Permit Issued
Issued on 10/25/2024
Issuing Office
Current Status
CofO Issued on 4/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/15/2024 APPLICANT
Assigned to Plan Check Engineer 5/21/2024 HUAN LE
Corrections Issued 5/23/2024 HUAN LE
Plan Check Approved 6/20/2024 ADAM HEGAZI
Issued 10/25/2024 APPLICANT
CofO in Progress 4/29/2025 CHRIS CHRISTENSEN
Permit Finaled 4/30/2025 JOHN JANSON
CofO Issued 4/30/2025 JOHN JANSON
Permit Finaled 4/30/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/4/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 6/4/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 6/4/2024 BIAINA HARITUNIAN
Sewer availability Cleared 6/4/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/13/2024 Partial Approval CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 11/20/2024 Conditional Approval HENRY KIM
Excavation/Setback/Form/Re-Bar 11/21/2024 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 12/27/2024 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 1/15/2025 Corrections Issued CHRIS CHRISTENSEN
PLUMBING-Rough 1/15/2025 Approved CHRIS CHRISTENSEN
Wood Frame 1/15/2025 Partial Approval CHRIS CHRISTENSEN
Interior/Exterior Lathing 1/22/2025 Partial Approval CHRIS CHRISTENSEN
Shower Pan 1/22/2025 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 1/27/2025 Not Ready for Inspection SCOTT SOBEL
PLUMBING-Rough 1/27/2025 Approved SCOTT SOBEL
Wood Frame 1/27/2025 Not Ready for Inspection SCOTT SOBEL
ELECTRICAL-Rough 2/4/2025 Approved CHRIS CHRISTENSEN
HVAC-Rough 2/4/2025 Approved CHRIS CHRISTENSEN
Insulation 2/4/2025 Approved CHRIS CHRISTENSEN
Wood Frame 2/4/2025 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 2/14/2025 Approved CHRIS CHRISTENSEN
Drywall Nailing 2/14/2025 Approved CHRIS CHRISTENSEN
Green Building Rough 2/14/2025 Approved CHRIS CHRISTENSEN
Sewer 2/24/2025 Approved STEVEN BACK
Underground Mechanical 2/24/2025 Approved STEVEN BACK
Interior/Exterior Lathing 3/5/2025 Approved CHRIS CHRISTENSEN
Final 4/15/2025 Corrections Issued CHRIS CHRISTENSEN
Footing/Foundation/Slab 4/15/2025 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 4/15/2025 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 4/15/2025 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 4/22/2025 Approved CHRIS CHRISTENSEN
Service/Power Release 4/22/2025 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 4/28/2025 Approved CHRIS CHRISTENSEN
Final 4/28/2025 OK to Issue CofO CHRIS CHRISTENSEN
HVAC-Final 4/28/2025 Approved CHRIS CHRISTENSEN
PLUMBING-Final 4/28/2025 Approved CHRIS CHRISTENSEN