7235 N YOLANDA AVE 91335

Certificate Information: 7235 N YOLANDA AVE 91335

Application / Permit
24014-20000-02043
Plan Check / Job No.
B24VN06727
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN. ADDITION TO (E) SFD
Permit Issued
Issued on 7/5/2024
Issuing Office
Current Status
CofO Issued on 11/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/14/2024 APPLICANT
Assigned to Plan Check Engineer 5/20/2024 NGHI SU
Corrections Issued 5/21/2024 NGHI SU
Applicant returned to address corrections 6/14/2024 NGHI SU
Plan Check Approved 6/18/2024 FERNANDO FLORES
Issued 7/5/2024 APPLICANT
CofO in Progress 9/27/2024 JEFFREY BULL
Permit Finaled 11/13/2024 JOHN JANSON
CofO Issued 11/13/2024 JOHN JANSON
Permit Finaled 11/13/2024 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/1/2024 TAL SHEMEN
Sewer availability Cleared 6/1/2024 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 6/5/2024 TAL SHEMEN

Contact Information

Contractor Owner-Builder       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/15/2024 Conditional Approval JEFFREY BULL
Footing/Foundation/Slab 7/16/2024 Approved JEFFREY BULL
Insulation 7/19/2024 Partial Approval JEFFREY BULL
PLUMBING-Rough 7/19/2024 Partial Approval JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 7/23/2024 Partial Approval JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 7/26/2024 Approved JEFFREY BULL
Green Building Rough 7/26/2024 Not Ready for Inspection JEFFREY BULL
Interior/Exterior Lathing 8/1/2024 Partial Approval JEFFREY BULL
ELECTRICAL-Rough 8/2/2024 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 8/2/2024 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Rough 8/6/2024 Corrections Issued SEAN WIRCH
Shower Pan 8/6/2024 Approved SEAN WIRCH
Insulation 8/8/2024 Approved JEFFREY BULL
Drywall Nailing 8/9/2024 Approved JEFFREY BULL
BUILDING-Rough-Frame 8/19/2024 Approved JEFFREY BULL
Final 8/19/2024 Corrections Issued JEFFREY BULL
Green Building Final 8/19/2024 Not Ready for Inspection JEFFREY BULL
Green Building Rough 8/19/2024 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 8/19/2024 SGSOV Not Ready JEFFREY BULL
Smoke Detectors 8/19/2024 Not Ready for Inspection JEFFREY BULL
Final 8/26/2024 Not Ready for Inspection JEFFREY BULL
Green Building Final 8/26/2024 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 8/26/2024 SGSOV Approved JEFFREY BULL
Smoke Detectors 8/26/2024 Not Ready for Inspection JEFFREY BULL
Final 8/27/2024 Not Ready for Inspection JEFFREY BULL
Smoke Detectors 8/27/2024 Approved JEFFREY BULL
Final 9/27/2024 OK to Issue CofO JEFFREY BULL