7663 N PASO ROBLES AVE 91406

Certificate Information: 7663 N PASO ROBLES AVE 91406

Application / Permit
24014-20000-02034
Plan Check / Job No.
B24VN06713
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 24'-6"X17'-6" IRREGULAR SHAPED ADDITION TO (E) SFD. ALL WORK PER WFPP.
Permit Issued
Issued on 5/20/2024
Issuing Office
Valley
Current Status
CofO Issued on 2/12/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/14/2024 APPLICANT
Assigned to Plan Check Engineer 5/14/2024 KAMYAR EMAMI
Corrections Issued 5/14/2024 KAMYAR EMAMI
Issued 5/20/2024 APPLICANT
CofO in Progress 2/2/2026 GAREN HAYRAPETYAN
Permit Finaled 2/12/2026 RUBEN SALAS
CofO Issued 2/12/2026 RUBEN SALAS
Permit Finaled 2/12/2026 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/17/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 5/17/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/14/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 6/18/2024 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 7/1/2024 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 8/2/2024 Approved RAUL OLAGI
Excavation/Setback/Form/Re-Bar 10/21/2024 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 10/21/2024 Conditional Approval SALVADOR MARTINEZ
BUILDING-Rough-Frame 11/8/2024 Approved SALVADOR MARTINEZ
ELECTRICAL-Rough 11/8/2024 Approved SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 11/8/2024 Approved SALVADOR MARTINEZ
Green Building Rough 11/8/2024 Approved SALVADOR MARTINEZ
Insulation 11/8/2024 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 11/8/2024 Approved SALVADOR MARTINEZ
Drywall Nailing 11/13/2024 Approved SALVADOR MARTINEZ
Green Building Rough 11/13/2024 Approved SALVADOR MARTINEZ
Final 11/20/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 11/20/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 11/20/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Smoke Detectors 11/20/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 11/26/2025 Partial Approval WAYNE REGESTER
Green Building Final 11/26/2025 Approved WAYNE REGESTER
SGSOV-Seismic Gas S/O Valve 11/26/2025 SGSOV Approved WAYNE REGESTER
Final 2/2/2026 OK to Issue CofO GAREN HAYRAPETYAN