13218 W MERCER ST 91331

Certificate Information: 13218 W MERCER ST 91331

Application / Permit
24014-20000-02024
Plan Check / Job No.
B24VN06680
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan New irregular shaped addition ( 28'0" x 45'6")to existing single family dwelling with interior remodel per WFPP. NFPA 13D Fire Sprinkler System is required.
Permit Issued
Issued on 7/21/2024
Issuing Office
Current Status
CofO Issued on 1/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2024 APPLICANT
Assigned to Plan Check Engineer 5/17/2024 NGHI SU
Corrections Issued 5/18/2024 NGHI SU
Applicant returned to address corrections 6/18/2024 NGHI SU
Plan Check Approved 6/24/2024 NGHI SU
Issued 7/21/2024 APPLICANT
CofO in Progress 1/24/2025 MICHEL ABAJAN
Permit Finaled 1/28/2025 RUBEN SALAS
CofO Issued 1/28/2025 RUBEN SALAS
Permit Finaled 1/28/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/23/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 5/23/2024 EDGAR ALCARAZ
Sewer availability Cleared 5/23/2024 EDGAR ALCARAZ

Contact Information

Contractor Refinish Plus Inc; Lic. No.: 1050293-B       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/9/2024 Conditional Approval ROBERT GOLD
PLUMBING-Rough 8/30/2024 Partial Approval SALVADOR MARTINEZ
Sewer 8/30/2024 Corrections Issued SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 9/6/2024 Approved MICHEL ABAJAN
Footing/Foundation/Slab 9/6/2024 Approved MICHEL ABAJAN
METHANE-Barrier 9/6/2024 Approved MICHEL ABAJAN
METHANE-Subgrade 9/6/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 9/6/2024 Partial Approval MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 9/9/2024 Partial Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 9/20/2024 Partial Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 9/20/2024 Partial Approval MICHEL ABAJAN
Green Building Rough 9/20/2024 Partial Inspection MICHEL ABAJAN
PLUMBING-Rough 9/20/2024 Approved MICHEL ABAJAN
ELECTRICAL-Rough 9/30/2024 Approved MICHEL ABAJAN
HVAC-Rough 9/30/2024 Partial Approval MICHEL ABAJAN
Interior/Exterior Lathing 9/30/2024 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 10/4/2024 Approved MICHEL ABAJAN
Green Building Rough 10/4/2024 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 10/4/2024 Approved MICHEL ABAJAN
Insulation 10/8/2024 Conditional Approval MICHEL ABAJAN
Drywall Nailing 10/10/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 10/10/2024 Approved MICHEL ABAJAN
Shower Pan 10/10/2024 Approved MICHEL ABAJAN
ELECTRICAL-Final 12/11/2024 Not Ready for Inspection MICHEL ABAJAN
Service/Power Release 12/11/2024 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Final 1/23/2025 Approved MICHEL ABAJAN
Final 1/23/2025 OK to Issue CofO MICHEL ABAJAN
Green Building Final 1/23/2025 Approved MICHEL ABAJAN
HVAC-Final 1/23/2025 Approved MICHEL ABAJAN
PLUMBING-Final 1/23/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 1/23/2025 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 1/23/2025 Approved MICHEL ABAJAN