11004 N WOODWARD AVE 91040

Certificate Information: 11004 N WOODWARD AVE 91040

Application / Permit
24014-20000-02017
Plan Check / Job No.
B24VN06667
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
DEMO EXISTING DETACHED GARAGE EXCEPT 6' OF EXTERIOR WALL & FOOTING TO REMAIN PER PLAN. THEN CONSTRUCT NEW IRR SHAPED ACCESSORY DWELLING UNIT ADDITION PER GCS 65852.2 (e)(1)(B) & LAMC 12.22A.33(c), (d) & (g). CONSTRUCTION PER ENGR DESIGN.
Permit Issued
Issued on 8/6/2024
Issuing Office
Metro
Current Status
CofO Issued on 4/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2024 APPLICANT
Assigned to Plan Check Engineer 5/17/2024 HAYATO TSUCHIYA
Corrections Issued 5/18/2024 HAYATO TSUCHIYA
Building Plans Picked Up 5/21/2024 APPLICANT
Plan Check Approved 6/28/2024 PINANK PATEL
Issued 8/6/2024 APPLICANT
CofO in Progress 3/21/2025 WILLIAM WREN
Permit Finaled 4/1/2025 RUBEN SALAS
CofO Issued 4/1/2025 RUBEN SALAS
Permit Finaled 4/1/2025 RUBEN SALAS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/24/2024 CHARLES POWELL
Address approval Cleared 5/31/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 5/31/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 5/31/2024 BIAINA HARITUNIAN
Sewer availability Cleared 5/31/2024 BIAINA HARITUNIAN
GPI Written Notices Cleared 6/28/2024 HAYATO TSUCHIYA

Contact Information

Contractor Ecostar Group Inc; Lic. No.: 1049320-B 19336 CALVERT ST      TARZANA, CA 91335
Engineer Ebrahimi,, Amirhosin; Lic. No.: C92049 8619 RESEDA BLVD UNIT 304B      NORTHRIDGE, CA 91324

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/28/2024 Corrections Issued WILLIAM WREN
Pre-Inspection 9/16/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 9/26/2024 Not Ready for Inspection WILLIAM WREN
Underground Mechanical 9/26/2024 Corrections Issued WILLIAM WREN
PLUMBING-Rough 9/30/2024 Partial Approval MICHEL ABAJAN
Underground Mechanical 9/30/2024 Partial Inspection MICHEL ABAJAN
Footing/Foundation/Slab 10/8/2024 Corrections Issued WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 10/28/2024 Approved WILLIAM WREN
Footing/Foundation/Slab 10/28/2024 Approved WILLIAM WREN
Green Building Rough 10/28/2024 Not Ready for Inspection WILLIAM WREN
ELECTRICAL-Rough 11/25/2024 Corrections Issued GREGG CUMMINGS
HVAC-Rough 11/25/2024 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 11/25/2024 Corrections Issued GREGG CUMMINGS
BUILDING-Rough-Frame 12/2/2024 Not Ready for Inspection WILLIAM WREN
ELECTRICAL-Rough 12/2/2024 Not Ready for Inspection WILLIAM WREN
Green Building Rough 12/2/2024 Not Ready for Inspection WILLIAM WREN
HVAC-Rough 12/2/2024 Approved WILLIAM WREN
PLUMBING-Rough 12/2/2024 Not Ready for Inspection WILLIAM WREN
ELECTRICAL-Rough 12/6/2024 Approved WILLIAM WREN
PLUMBING-Rough 12/6/2024 Approved WILLIAM WREN
Shower Pan 12/6/2024 Approved WILLIAM WREN
Interior/Exterior Lathing 12/17/2024 Partial Approval MATTHEW NELSON
Insulation 12/23/2024 Corrections Issued WILLIAM WREN
BUILDING-Rough-Frame 1/6/2025 Approved WILLIAM WREN
Drywall Nailing 1/6/2025 Approved WILLIAM WREN
Green Building Rough 1/6/2025 Approved WILLIAM WREN
Interior/Exterior Lathing 1/6/2025 Approved WILLIAM WREN
Final 3/5/2025 Corrections Issued WILLIAM WREN
Green Building Final 3/5/2025 Not Ready for Inspection WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 3/5/2025 SGSOV Approved WILLIAM WREN
Smoke Detectors 3/5/2025 Approved WILLIAM WREN
Final 3/10/2025 OK to Issue CofO WILLIAM WREN
Green Building Final 3/10/2025 Approved WILLIAM WREN