15946 W DEVONSHIRE ST 91344

Certificate Information: 15946 W DEVONSHIRE ST 91344

Application / Permit
24014-20000-02007
Plan Check / Job No.
B24VN06642
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: ADDITION TO (E) F GARAGE TO CONVERT INTO NEW ACCESSROY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 6/28/2024
Issuing Office
Current Status
CofO Issued on 5/19/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2024 APPLICANT
Assigned to Plan Check Engineer 5/17/2024 MOHAMMAD ESMAILI
Corrections Issued 5/21/2024 MOHAMMAD ESMAILI
Applicant returned to address corrections 6/17/2024 MOHAMMAD ESMAILI
Plan Check Approved 6/26/2024 MOHAMMAD ESMAILI
Issued 6/28/2024 APPLICANT
CofO in Progress 3/31/2026 CHRISTOPHER ROJAS
Permit Finaled 5/19/2026 RUBEN SALAS
CofO Issued 5/19/2026 RUBEN SALAS
Permit Finaled 5/19/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/1/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 6/1/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/3/2024 CARLOS AGUILERA
Sewer availability Cleared 6/4/2024 CARLOS AGUILERA
GPI Written Notices Cleared 6/26/2024 MOHAMMAD ESMAILI
Grading Pre-Inspection Cleared 6/26/2024 CHARLES POWELL

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/2/2024 Partial Approval KEVIN BERBERYAN
Footing/Foundation/Slab 12/19/2024 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 2/25/2025 Corrections Issued LOUIS ESCOTO
Floor/Roof Diaphrgm/Shear Wall 2/27/2025 Corrections Issued MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 2/28/2025 Corrections Issued LOUIS ESCOTO
BUILDING-Rough-Frame 3/10/2025 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 3/10/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 4/15/2025 Corrections Issued CHRISTOPHER ROJAS
Interior/Exterior Lathing 4/15/2025 Partial Approval CHRISTOPHER ROJAS
Underground Mechanical 4/21/2025 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/25/2025 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 4/25/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 4/28/2025 Approved CHRISTOPHER ROJAS
HVAC-Rough 4/28/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 5/2/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 5/2/2025 Approved CHRISTOPHER ROJAS
Insulation 5/9/2025 Approved LOUIS ESCOTO
Drywall Nailing 5/14/2025 Approved KEVIN BERBERYAN
Shower Pan 6/13/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 6/27/2025 Partial Approval CHRISTOPHER ROJAS
Gas Test 12/29/2025 Corrections Issued CHRISTOPHER ROJAS
Special/Order Compliance 12/29/2025 Approved CHRISTOPHER ROJAS
Gas Test 1/23/2026 Approved DAVID ANDERSON
ELECTRICAL-Final 2/13/2026 Corrections Issued CHRISTOPHER ROJAS
Final 2/13/2026 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 2/13/2026 Conditional Approval CHRISTOPHER ROJAS
HVAC-Final 2/13/2026 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Final 2/13/2026 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 2/13/2026 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 2/13/2026 Approved CHRISTOPHER ROJAS
Final 3/11/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Final 3/11/2026 Approved CHRISTOPHER ROJAS
Final 3/31/2026 OK to Issue CofO CHRISTOPHER ROJAS
Service/Power Release 3/31/2026 Approved CHRISTOPHER ROJAS