11053 W CALIFA ST 91601
Certificate Information: 11053 W CALIFA ST 91601
- Application / Permit
- 24014-20000-01992
- Plan Check / Job No.
- B24VN06575
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE WITH 30' x 16'6" IRREG.SHAPED ADDITIO TO A NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 6/21/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 5/16/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 5/20/2024 | APPLICANT |
| Applicant returned to address corrections | 6/18/2024 | ANGELICA DAVE |
| Plan Check Approved | 6/20/2024 | MIROOSH KHACHATOORIAN |
| Issued | 6/21/2024 | APPLICANT |
| CofO in Progress | 2/13/2026 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 3/10/2026 | RUBEN SALAS |
| CofO Issued | 3/10/2026 | RUBEN SALAS |
| Permit Finaled | 3/10/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/20/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 5/20/2024 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 5/22/2024 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/12/2024 | CARLOS AGUILERA |
| Hold | Cleared | 8/27/2024 | MARIA VENDIVIL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/30/2024 | Corrections Issued | JOSE AVILA |
| Pre-Inspection | 9/5/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 9/9/2024 | Partial Approval | JOSE AVILA |
| Underground Mechanical | 9/18/2024 | Partial Approval | JOSE AVILA |
| Footing/Foundation/Slab | 9/30/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Deputy Wood Construction | 10/30/2024 | Conditional Approval | JUAN VALENZUELA |
| Wood Frame | 10/31/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Sewer | 11/18/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 12/2/2024 | No Access for Inspection | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 12/2/2024 | No Access for Inspection | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 12/2/2024 | No Access for Inspection | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 12/2/2024 | No Access for Inspection | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 12/24/2024 | Partial Approval | JOSE AVILA |
| PLUMBING-Rough | 12/24/2024 | Approved | JOSE AVILA |
| Special/Order Compliance | 12/24/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 1/10/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 1/10/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 1/28/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 1/28/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 1/28/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 4/9/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 4/9/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 4/9/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 5/2/2025 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 5/19/2025 | Approved | JOSE AVILA |
| Drywall Nailing | 6/3/2025 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 6/23/2025 | Not Ready for Inspection | JOSE AVILA |
| Interior/Exterior Lathing | 8/1/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Pre-Inspection | 8/13/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Final | 1/5/2026 | Corrections Issued | JOSE AVILA |
| Final | 1/12/2026 | Corrections Issued | JOSE AVILA |
| Final | 1/20/2026 | Not Ready for Inspection | JOSE AVILA |
| Final | 2/11/2026 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 2/11/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 2/11/2026 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 2/11/2026 | Approved | ROBERTO PALACIOS-LOPEZ |