16639 W CHATSWORTH ST 91344

Certificate Information: 16639 W CHATSWORTH ST 91344

Application / Permit
24014-20000-01967
Plan Check / Job No.
B24VN06503
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING 339 SF GARAGE TO ADU & 394 SF ADDITION TO ADU PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g)
Permit Issued
Issued on 12/1/2024
Issuing Office
Current Status
CofO Issued on 3/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/10/2024 APPLICANT
Assigned to Plan Check Engineer 5/16/2024 NGHI SU
Corrections Issued 2 5/17/2024 NGHI SU
Submitted for Second Quality Review 11/13/2024 NGHI SU
Plan Check Approved 11/20/2024 NGHI SU
Issued 12/1/2024 APPLICANT
CofO in Progress 2/10/2026 CHRISTOPHER ROJAS
Permit Finaled 3/3/2026 RUBEN SALAS
Permit Finaled 3/3/2026 RUBEN SALAS
CofO Issued 3/3/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/31/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 5/31/2024 BIAINA HARITUNIAN
Sewer availability Cleared 10/3/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 11/5/2024 ROSE MARIE SMITH

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 4/16/2025 Approved NICHOLAS TROWBRIDGE
Underground Mechanical 4/16/2025 Partial Approval NICHOLAS TROWBRIDGE
Underground Mechanical 6/24/2025 Partial Approval CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 6/26/2025 Approved CHRISTOPHER ROJAS
Grounding or Bonding 6/26/2025 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 8/13/2025 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 8/13/2025 Partial Approval CHRISTOPHER ROJAS
Underground Mechanical 8/13/2025 Partial Approval CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 8/19/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 9/10/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 9/10/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Interior/Exterior Lathing 9/10/2025 Partial Approval CHRISTOPHER ROJAS
Rough-Elec/Plmb/HVAC 9/10/2025 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 9/22/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 9/22/2025 Approved CHRISTOPHER ROJAS
Insulation 9/22/2025 Approved CHRISTOPHER ROJAS
Rough-Elec/Plmb/HVAC 9/22/2025 Approved CHRISTOPHER ROJAS
Deputy Wood Construction 9/26/2025 Conditional Approval RAUL OLAGI
Drywall Nailing 10/6/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 10/6/2025 Approved CHRISTOPHER ROJAS
Shower Pan 10/6/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 1/13/2026 Corrections Issued CHRISTOPHER ROJAS
Final 1/13/2026 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 1/13/2026 Approved CHRISTOPHER ROJAS
Green Building Final 1/13/2026 Approved CHRISTOPHER ROJAS
HVAC-Final 1/13/2026 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Final 1/13/2026 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 1/13/2026 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 1/13/2026 Approved CHRISTOPHER ROJAS
HVAC-Final 1/26/2026 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 1/26/2026 Approved ROBERTO PALACIOS-LOPEZ
Final 2/6/2026 OK to Issue CofO CHRISTOPHER ROJAS