14124 W OSBORNE ST 91402

Certificate Information: 14124 W OSBORNE ST 91402

Application / Permit
24014-20000-01962
Plan Check / Job No.
B24VN06490
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan: Garage Conversion to ADU w/Addition and Covered Patio per LAMC 12.22 A.33 (c) and (d)
Permit Issued
Issued on 12/30/2024
Issuing Office
Current Status
CofO Issued on 3/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/22/2024 APPLICANT
Assigned to Plan Check Engineer 5/29/2024 DAVID CASTILLO
Corrections Issued 6/3/2024 DAVID CASTILLO
Applicant returned to address corrections 11/6/2024 DAVID CASTILLO
Applicant returned to address corrections 11/28/2024 DAVID CASTILLO
Plan Check Approved 12/4/2024 DAVID CASTILLO
Issued 12/30/2024 APPLICANT
CofO in Progress 2/4/2026 VINCENT HANLEY
Permit Finaled 3/10/2026 RUBEN SALAS
CofO Issued 3/10/2026 RUBEN SALAS
Permit Finaled 3/10/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/8/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 6/8/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/10/2024 CARLOS AGUILERA
Sewer availability Cleared 6/10/2024 CARLOS AGUILERA
Trees in Parkway Cleared 9/9/2024 ADALBERTO VERA
Construction within easement Cleared 10/23/2024 TINA MIRANDA
Permit Cleared 11/4/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Baluyut,, Agustin Pangilinan; Lic. No.: C66025 22828 S CYPRESS DR      CARSON, CA 90745

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/21/2025 Approved VINCENT HANLEY
PLUMBING-Rough 2/20/2025 Partial Approval VINCENT HANLEY
Sewer 2/20/2025 Approved VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 2/24/2025 Approved MICHEL ABAJAN
Footing/Foundation/Slab 2/24/2025 Conditional Approval MICHEL ABAJAN
BUILDING-Rough-Frame 5/2/2025 Not Ready for Inspection VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 5/2/2025 Partial Approval VINCENT HANLEY
Green Building Rough 5/2/2025 Not Ready for Inspection VINCENT HANLEY
Wood Frame 5/2/2025 Not Ready for Inspection VINCENT HANLEY
Rough-Elec/Plmb/HVAC 7/7/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 7/8/2025 Corrections Issued VINCENT HANLEY
Green Building Rough 7/8/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 7/22/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 7/22/2025 Approved VINCENT HANLEY
Insulation 7/22/2025 Approved VINCENT HANLEY
Interior/Exterior Lathing 7/22/2025 Partial Approval VINCENT HANLEY
Shower Pan 7/22/2025 Approved VINCENT HANLEY
Drywall Nailing 8/15/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 9/4/2025 Approved VINCENT HANLEY
Final 11/13/2025 Corrections Issued RYAN SALAZAR
Footing/Foundation/Slab 11/13/2025 Approved RYAN SALAZAR
Green Building Final 11/13/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 11/13/2025 SGSOV Approved RYAN SALAZAR
Smoke Detectors 11/13/2025 Approved RYAN SALAZAR
Final 11/24/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Final 12/19/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Final 1/7/2026 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Final 1/20/2026 Corrections Issued VINCENT HANLEY
Final 1/20/2026 Corrections Issued VINCENT HANLEY
HVAC-Final 1/20/2026 Approved VINCENT HANLEY
PLUMBING-Final 1/20/2026 Corrections Issued VINCENT HANLEY
ELECTRICAL-Final 2/3/2026 Approved VINCENT HANLEY
Final 2/3/2026 OK to Issue CofO VINCENT HANLEY
HVAC-Final 2/3/2026 Approved VINCENT HANLEY
PLUMBING-Final 2/3/2026 Approved VINCENT HANLEY