19465 W VINTAGE ST 91324
Certificate Information: 19465 W VINTAGE ST 91324
- Application / Permit
- 24014-20000-01951
- Plan Check / Job No.
- B24VN06467
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF A WALK IN CLOSET TO THE (E) BEDROOM TO (E) SFD.
- Permit Issued
- Issued on 10/15/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2024 | LUISANGEL VALENZUELA |
| Corrections Issued | 5/9/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 10/1/2024 | SERGIO MUNIZ |
| Issued | 10/15/2024 | APPLICANT |
| CofO in Progress | 1/31/2025 | DAVID SCANTLIN |
| CofO Issued | 2/5/2025 | JOHN JANSON |
| Permit Finaled | 2/5/2025 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/24/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/26/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Clayton,, Andrew; Lic. No.: C85452 | 10211 LEMONA AVE MISSION HILLS, CA 91345 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/18/2024 | Conditional Approval | DAVID SCANTLIN |
| Footing/Foundation/Slab | 11/21/2024 | Approved | DAVID SCANTLIN |
| Wood Frame | 11/27/2024 | Partial Approval | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2024 | Partial Approval | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 12/17/2024 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Rough | 12/17/2024 | Approved | DAVID SCANTLIN |
| Green Building Rough | 12/17/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Rough | 12/20/2024 | Approved | DAVID SCANTLIN |
| Insulation | 12/20/2024 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 12/20/2024 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 12/31/2024 | Approved | DAVID SCANTLIN |
| Final | 1/30/2025 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 1/30/2025 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 1/30/2025 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 1/30/2025 | Approved | DAVID SCANTLIN |
| Final | 1/31/2025 | OK to Issue CofO | DAVID SCANTLIN |