1328 S COCHRAN AVE 1-4 90019
Certificate Information: 1328 S COCHRAN AVE 1-4 90019
- Application / Permit
- 24014-20000-01939
- Plan Check / Job No.
- B24VN06419
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- ADD 18'-11" X 24'-11" ACCESSORY DWELLING UNIT PER TO EXISTING 3-UNIT APARTMENT
- Permit Issued
- Issued on 6/18/2025
- Issuing Office
- Current Status
- Issued on 6/18/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2024 | SELLA BENYAMIN |
| Assigned to Zoning Architect | 5/23/2024 | KAITA SAITO |
| Corrections Issued | 5/30/2024 | SELLA BENYAMIN |
| Green Plans Picked Up | 6/3/2024 | APPLICANT |
| Quality Review Completed | 6/10/2024 | STEVEN KIM |
| Building Plans Picked Up | 6/18/2024 | APPLICANT |
| Plan Check Approved | 6/18/2025 | SELLA BENYAMIN |
| Issued | 6/18/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/15/2024 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2024 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 7/15/2024 | JEANIE LAM |
| Sewer availability | Cleared | 7/15/2024 | JEANIE LAM |
| Green Code | Cleared | 9/13/2024 | MICHAEL AYERS |
| Zoning Plan Check | Cleared | 6/3/2025 | KAITA SAITO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/27/2025 | Corrections Issued | CHRISTOPHER BLACKWOOD |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2025 | Partial Approval | PAUL BAZERKANIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2025 | Partial Approval | PAUL BAZERKANIAN |
| Insulation | 8/1/2025 | Partial Approval | PAUL BAZERKANIAN |
| Interior/Exterior Lathing | 8/1/2025 | Partial Approval | PAUL BAZERKANIAN |
| Drywall Nailing | 8/4/2025 | Partial Approval | PAUL BAZERKANIAN |
| Final | 8/18/2025 | Partial Approval | PAUL BAZERKANIAN |
| Footing/Foundation/Slab | 8/18/2025 | Approved | PAUL BAZERKANIAN |
| Green Building Final | 8/18/2025 | Approved | PAUL BAZERKANIAN |
| Green Building Rough | 8/18/2025 | Approved | PAUL BAZERKANIAN |
| METHANE-Barrier | 8/18/2025 | Approved | PAUL BAZERKANIAN |
| METHANE-Final | 8/18/2025 | Approved | PAUL BAZERKANIAN |
| METHANE-Rough | 8/18/2025 | Approved | PAUL BAZERKANIAN |
| METHANE-Subgrade | 8/18/2025 | Approved | PAUL BAZERKANIAN |
| SGSOV-Seismic Gas S/O Valve | 8/18/2025 | SGSOV Approved | PAUL BAZERKANIAN |
| Smoke Detectors | 8/18/2025 | Approved | PAUL BAZERKANIAN |
| Wood Frame | 8/18/2025 | Approved | PAUL BAZERKANIAN |