8751 N ODESSA AVE 91343
Certificate Information: 8751 N ODESSA AVE 91343
- Application / Permit
- 24014-20000-01921
- Plan Check / Job No.
- B24VN06357
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan. Rear addition and remodel of existing single family dwelling with attached garage.
- Permit Issued
- Issued on 7/17/2024
- Issuing Office
- Current Status
- CofO Issued on 5/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/15/2024 | ADAM HEGAZI |
| Corrections Issued | 5/16/2024 | ADAM HEGAZI |
| Plan Check Approved | 7/12/2024 | ADAM HEGAZI |
| Issued | 7/17/2024 | APPLICANT |
| CofO in Progress | 4/29/2025 | SALVADOR MARTINEZ |
| Permit Finaled | 5/6/2025 | RUBEN SALAS |
| Permit Finaled | 5/6/2025 | RUBEN SALAS |
| CofO Issued | 5/6/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/17/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/20/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: NA93320 | , |
Inspector Information
| JOAQUIN GREENOUGH, (818) 374-1180 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/10/2024 | Partial Approval | SALVADOR MARTINEZ |
| PLUMBING-Rough | 10/10/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 10/16/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 10/22/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Special/Order Compliance | 10/22/2024 | Partial Inspection | RAUL OLAGI |
| PLUMBING-Rough | 10/25/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 10/31/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 11/4/2024 | Partial Approval | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 11/25/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 11/25/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Rough | 11/25/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 12/6/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Green Building Rough | 12/6/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| HVAC-Rough | 12/6/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 12/6/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 12/9/2024 | Approved | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Rough | 12/13/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| HVAC-Rough | 12/13/2024 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 12/17/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2024 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 12/17/2024 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 12/18/2024 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2024 | Partial Approval | GAREN HAYRAPETYAN |
| HVAC-Rough | 12/18/2024 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 12/23/2024 | Approved | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2024 | Approved | SALVADOR MARTINEZ |
| Green Building Rough | 12/23/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 12/23/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Insulation | 12/31/2024 | Partial Approval | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 12/31/2024 | Approved | MICHAEL CORTEZ |
| Insulation | 1/2/2025 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 1/2/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 1/14/2025 | Approved | LOUIS ESCOTO |
| BUILDING-Rough-Frame | 3/14/2025 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 3/14/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 3/14/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 3/14/2025 | Approved | SALVADOR MARTINEZ |
| Green Building Final | 3/14/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Green Building Rough | 3/14/2025 | Approved | SALVADOR MARTINEZ |
| HVAC-Final | 3/14/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 3/14/2025 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 3/14/2025 | SGSOV Not Ready | SALVADOR MARTINEZ |
| Smoke Detectors | 3/14/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 4/14/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 4/14/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 4/14/2025 | Approved | SALVADOR MARTINEZ |
| HVAC-Final | 4/14/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 4/14/2025 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 4/14/2025 | SGSOV Approved | SALVADOR MARTINEZ |
| Smoke Detectors | 4/14/2025 | Partial Inspection | SALVADOR MARTINEZ |
| Final | 4/17/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Service/Power Release | 4/17/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Smoke Detectors | 4/17/2025 | Approved | SALVADOR MARTINEZ |
| Final | 4/28/2025 | OK to Issue CofO | SALVADOR MARTINEZ |
| Service/Power Release | 4/28/2025 | Approved | SALVADOR MARTINEZ |