5528 N CARTWRIGHT AVE 91601
Certificate Information: 5528 N CARTWRIGHT AVE 91601
- Application / Permit
- 24014-20000-01919
- Plan Check / Job No.
- B24VN06348
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: REMODEL, CONVERT AND ENCLOSE ATTACHED REAR PATIO COVER, AND (N) BEDROOM ADDITION TO (E) S.F.D. PER ENGINEERING
- Permit Issued
- Issued on 7/9/2024
- Issuing Office
- Current Status
- CofO Issued on 12/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/10/2024 | ALFRED RAMIREZ |
| Corrections Issued | 5/11/2024 | ALFRED RAMIREZ |
| Plan Check Approved | 6/12/2024 | ALFRED RAMIREZ |
| Issued | 7/9/2024 | APPLICANT |
| CofO in Progress | 10/18/2024 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 12/4/2024 | RUBEN SALAS |
| CofO Issued | 12/4/2024 | RUBEN SALAS |
| Permit Finaled | 12/4/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/11/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 6/11/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 6/11/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Bayani-Rad,, Padra; Lic. No.: C86320 | 15901 HAWTHORNE BLVD UNIT 220 LAWNDALE, CA 90260 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/16/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 7/30/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 7/30/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| METHANE-Barrier | 7/30/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| METHANE-Subgrade | 7/30/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 8/5/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| METHANE-Rough | 8/5/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Wood Frame | 8/5/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Insulation | 8/7/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 8/20/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| METHANE-Rough | 8/20/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 8/20/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 8/23/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Insulation | 8/23/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Wood Frame | 8/23/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Deputy Wood Construction | 8/26/2024 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 8/28/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 8/28/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 8/30/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 9/16/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 9/16/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 9/16/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 9/19/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 9/19/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 9/19/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 9/24/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 10/7/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 10/7/2024 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 10/7/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 10/11/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 10/11/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 10/11/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 10/11/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 10/11/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 10/17/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 10/17/2024 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 10/17/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 10/17/2024 | Approved | ROBERTO PALACIOS-LOPEZ |