11568 W BARMAN ST 90230
Certificate Information: 11568 W BARMAN ST 90230
- Application / Permit
- 24014-20000-01918
- Plan Check / Job No.
- B24VN06345
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- IRREGULAR ADDITION 22' X 42' AND CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP
- Permit Issued
- Issued on 8/22/2024
- Issuing Office
- Current Status
- CofO Issued on 6/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2024 | JESSE ARELLANO |
| Corrections Issued | 5/14/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 5/15/2024 | APPLICANT |
| Issued | 8/22/2024 | APPLICANT |
| CofO in Progress | 6/23/2025 | MICHAEL ALLEN |
| Permit Finaled | 6/25/2025 | RICHARD STEINBACH |
| CofO Issued | 6/25/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/25/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 5/15/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2024 | DARIN LAM |
| Sewer availability | Cleared | 5/20/2024 | DARIN LAM |
| Specific Plan | Cleared | 6/11/2024 | FREDDY GARCIA |
| Roof/Waste drainage to street | Cleared | 7/10/2024 | LIAM ODONOVAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/22/2025 | Partial Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 2/3/2025 | Corrections Issued | MICHAEL ALLEN |
| Underground Mechanical | 2/3/2025 | Partial Approval | MICHAEL ALLEN |
| Excavation/Setback/Form/Re-Bar | 2/10/2025 | Corrections Issued | KIRK SANDERS |
| Excavation/Setback/Form/Re-Bar | 2/21/2025 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 2/21/2025 | Approved | BOBBY KEY |
| Sewer | 2/28/2025 | Approved | REGINA MENDEZ |
| ELECTRICAL-Rough | 3/11/2025 | Partial Approval | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2025 | Partial Approval | MICHAEL ALLEN |
| HVAC-Rough | 3/11/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| PLUMBING-Rough | 3/11/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| Wood Frame | 3/11/2025 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 3/17/2025 | Corrections Issued | RUBEN RIVAS |
| ELECTRICAL-Rough | 3/17/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2025 | Approved | RUBEN RIVAS |
| Green Building Rough | 3/17/2025 | Not Ready for Inspection | RUBEN RIVAS |
| HVAC-Rough | 3/17/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Interior/Exterior Lathing | 3/17/2025 | Not Ready for Inspection | RUBEN RIVAS |
| PLUMBING-Rough | 3/17/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Special/Order Compliance | 3/17/2025 | Partial Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 3/21/2025 | Not Ready for Inspection | RUBEN RIVAS |
| ELECTRICAL-Rough | 3/21/2025 | Partial Approval | RUBEN RIVAS |
| Green Building Rough | 3/21/2025 | Not Ready for Inspection | RUBEN RIVAS |
| HVAC-Rough | 3/21/2025 | Partial Approval | RUBEN RIVAS |
| PLUMBING-Rough | 3/21/2025 | Partial Approval | RUBEN RIVAS |
| Special/Order Compliance | 3/21/2025 | Partial Inspection | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 4/2/2025 | Partial Approval | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2025 | Approved | RUBEN RIVAS |
| HVAC-Rough | 4/2/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Interior/Exterior Lathing | 4/2/2025 | Approved | RUBEN RIVAS |
| PLUMBING-Rough | 4/2/2025 | Approved | RUBEN RIVAS |
| Special/Order Compliance | 4/2/2025 | Partial Inspection | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 4/8/2025 | Partial Approval | MICHAEL ALLEN |
| ELECTRICAL-Rough | 4/8/2025 | Approved | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2025 | Approved | MICHAEL ALLEN |
| Green Building Rough | 4/8/2025 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 4/8/2025 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 4/8/2025 | Partial Approval | MICHAEL ALLEN |
| PLUMBING-Rough | 4/8/2025 | Approved | MICHAEL ALLEN |
| Shower Pan | 4/8/2025 | Approved | MICHAEL ALLEN |
| Wood Frame | 4/8/2025 | Approved | MICHAEL ALLEN |
| Insulation | 4/10/2025 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 4/15/2025 | Approved | JAYLIN GRAVITTE |
| Drywall Nailing | 4/15/2025 | Approved | JAYLIN GRAVITTE |
| Green Building Rough | 4/15/2025 | Approved | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 4/15/2025 | Approved | JAYLIN GRAVITTE |
| Green Building Final | 6/10/2025 | Conditional Approval | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 6/10/2025 | SGSOV Approved | MICHAEL ALLEN |
| Smoke Detectors | 6/10/2025 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Final | 6/12/2025 | Corrections Issued | RUBEN RIVAS |
| Final | 6/12/2025 | Corrections Issued | RUBEN RIVAS |
| HVAC-Final | 6/12/2025 | Corrections Issued | RUBEN RIVAS |
| PLUMBING-Final | 6/12/2025 | Approved | RUBEN RIVAS |
| Service/Power Release | 6/12/2025 | Not Ready for Inspection | RUBEN RIVAS |
| ELECTRICAL-Final | 6/17/2025 | Approved | MICHAEL ALLEN |
| Final | 6/17/2025 | Conditional Approval | MICHAEL ALLEN |
| Green Building Final | 6/17/2025 | Approved | MICHAEL ALLEN |
| HVAC-Final | 6/17/2025 | Approved | MICHAEL ALLEN |
| Final | 6/23/2025 | OK to Issue CofO | MICHAEL ALLEN |