11568 W BARMAN ST 90230

Certificate Information: 11568 W BARMAN ST 90230

Application / Permit
24014-20000-01918
Plan Check / Job No.
B24VN06345
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
IRREGULAR ADDITION 22' X 42' AND CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP
Permit Issued
Issued on 8/22/2024
Issuing Office
Current Status
CofO Issued on 6/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/7/2024 APPLICANT
Assigned to Plan Check Engineer 5/13/2024 JESSE ARELLANO
Corrections Issued 5/14/2024 JESSE ARELLANO
Building Plans Picked Up 5/15/2024 APPLICANT
Issued 8/22/2024 APPLICANT
CofO in Progress 6/23/2025 MICHAEL ALLEN
Permit Finaled 6/25/2025 RICHARD STEINBACH
CofO Issued 6/25/2025 RICHARD STEINBACH
Permit Finaled 6/25/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 5/15/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 5/20/2024 DARIN LAM
Sewer availability Cleared 5/20/2024 DARIN LAM
Specific Plan Cleared 6/11/2024 FREDDY GARCIA
Roof/Waste drainage to street Cleared 7/10/2024 LIAM ODONOVAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/22/2025 Partial Inspection ANTHONY EGSON
PLUMBING-Rough 2/3/2025 Corrections Issued MICHAEL ALLEN
Underground Mechanical 2/3/2025 Partial Approval MICHAEL ALLEN
Excavation/Setback/Form/Re-Bar 2/10/2025 Corrections Issued KIRK SANDERS
Excavation/Setback/Form/Re-Bar 2/21/2025 Approved BOBBY KEY
Footing/Foundation/Slab 2/21/2025 Approved BOBBY KEY
Sewer 2/28/2025 Approved REGINA MENDEZ
ELECTRICAL-Rough 3/11/2025 Partial Approval MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 3/11/2025 Partial Approval MICHAEL ALLEN
HVAC-Rough 3/11/2025 Not Ready for Inspection MICHAEL ALLEN
PLUMBING-Rough 3/11/2025 Not Ready for Inspection MICHAEL ALLEN
Wood Frame 3/11/2025 Approved MICHAEL ALLEN
BUILDING-Rough-Frame 3/17/2025 Corrections Issued RUBEN RIVAS
ELECTRICAL-Rough 3/17/2025 Not Ready for Inspection RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 3/17/2025 Approved RUBEN RIVAS
Green Building Rough 3/17/2025 Not Ready for Inspection RUBEN RIVAS
HVAC-Rough 3/17/2025 Not Ready for Inspection RUBEN RIVAS
Interior/Exterior Lathing 3/17/2025 Not Ready for Inspection RUBEN RIVAS
PLUMBING-Rough 3/17/2025 Not Ready for Inspection RUBEN RIVAS
Special/Order Compliance 3/17/2025 Partial Inspection BOBBY KEY
BUILDING-Rough-Frame 3/21/2025 Not Ready for Inspection RUBEN RIVAS
ELECTRICAL-Rough 3/21/2025 Partial Approval RUBEN RIVAS
Green Building Rough 3/21/2025 Not Ready for Inspection RUBEN RIVAS
HVAC-Rough 3/21/2025 Partial Approval RUBEN RIVAS
PLUMBING-Rough 3/21/2025 Partial Approval RUBEN RIVAS
Special/Order Compliance 3/21/2025 Partial Inspection STEPHANIE SWANSON
ELECTRICAL-Rough 4/2/2025 Partial Approval RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 4/2/2025 Approved RUBEN RIVAS
HVAC-Rough 4/2/2025 Not Ready for Inspection RUBEN RIVAS
Interior/Exterior Lathing 4/2/2025 Approved RUBEN RIVAS
PLUMBING-Rough 4/2/2025 Approved RUBEN RIVAS
Special/Order Compliance 4/2/2025 Partial Inspection TEMISTOCLES CAAL
BUILDING-Rough-Frame 4/8/2025 Partial Approval MICHAEL ALLEN
ELECTRICAL-Rough 4/8/2025 Approved MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 4/8/2025 Approved MICHAEL ALLEN
Green Building Rough 4/8/2025 Approved MICHAEL ALLEN
HVAC-Rough 4/8/2025 Approved MICHAEL ALLEN
Interior/Exterior Lathing 4/8/2025 Partial Approval MICHAEL ALLEN
PLUMBING-Rough 4/8/2025 Approved MICHAEL ALLEN
Shower Pan 4/8/2025 Approved MICHAEL ALLEN
Wood Frame 4/8/2025 Approved MICHAEL ALLEN
Insulation 4/10/2025 Approved MICHAEL ALLEN
BUILDING-Rough-Frame 4/15/2025 Approved JAYLIN GRAVITTE
Drywall Nailing 4/15/2025 Approved JAYLIN GRAVITTE
Green Building Rough 4/15/2025 Approved JAYLIN GRAVITTE
Interior/Exterior Lathing 4/15/2025 Approved JAYLIN GRAVITTE
Green Building Final 6/10/2025 Conditional Approval MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 6/10/2025 SGSOV Approved MICHAEL ALLEN
Smoke Detectors 6/10/2025 Approved MICHAEL ALLEN
ELECTRICAL-Final 6/12/2025 Corrections Issued RUBEN RIVAS
Final 6/12/2025 Corrections Issued RUBEN RIVAS
HVAC-Final 6/12/2025 Corrections Issued RUBEN RIVAS
PLUMBING-Final 6/12/2025 Approved RUBEN RIVAS
Service/Power Release 6/12/2025 Not Ready for Inspection RUBEN RIVAS
ELECTRICAL-Final 6/17/2025 Approved MICHAEL ALLEN
Final 6/17/2025 Conditional Approval MICHAEL ALLEN
Green Building Final 6/17/2025 Approved MICHAEL ALLEN
HVAC-Final 6/17/2025 Approved MICHAEL ALLEN
Final 6/23/2025 OK to Issue CofO MICHAEL ALLEN