22727 W SYLVAN ST 91367

Certificate Information: 22727 W SYLVAN ST 91367

Application / Permit
24014-20000-01911
Plan Check / Job No.
B24VN06332
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
13'-9"x 23'-9" ADDITION AND REMODEL TO (E) SFD
Permit Issued
Issued on 6/20/2024
Issuing Office
Current Status
CofO Issued on 1/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/7/2024 APPLICANT
Assigned to Plan Check Engineer 5/13/2024 JESSE ARELLANO
Corrections Issued 5/14/2024 JESSE ARELLANO
Building Plans Picked Up 5/21/2024 APPLICANT
Plan Check Approved 6/20/2024 ALEC MOUSAKHANIAN
Issued 6/20/2024 APPLICANT
CofO in Progress 11/9/2024 GEVORK IPCHYAN
CofO in Progress 1/9/2025 HENRY KIM
Permit Finaled 1/14/2025 JOHN JANSON
CofO Issued 1/14/2025 JOHN JANSON
Permit Finaled 1/14/2025 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/25/2024 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 5/28/2024 BRYAN GODINEZ
Grading Pre-Inspection Cleared 6/3/2024 CHARLES POWELL

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/27/2024 Corrections Issued GEVORK IPCHYAN
PLUMBING-Rough 6/27/2024 Partial Approval GEVORK IPCHYAN
Footing/Foundation/Slab 7/1/2024 Approved HORACE FULTZ
Deputy Steel/Welding 7/11/2024 Conditional Approval TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 7/31/2024 Partial Approval GEVORK IPCHYAN
Deputy Wood Construction 8/1/2024 Conditional Approval TROY SANDERS
Rough-Elec/Plmb/HVAC 8/5/2024 Partial Approval GEVORK IPCHYAN
Insulation 8/9/2024 Approved TROY SANDERS
Drywall Nailing 8/13/2024 Approved GEVORK IPCHYAN
BUILDING-Rough-Frame 10/25/2024 Approved GEVORK IPCHYAN
Final 10/25/2024 Not Ready for Inspection GEVORK IPCHYAN
Green Building Final 10/25/2024 Not Ready for Inspection GEVORK IPCHYAN
Green Building Rough 10/25/2024 Approved GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 10/25/2024 SGSOV Approved GEVORK IPCHYAN
Smoke Detectors 10/25/2024 Approved GEVORK IPCHYAN
ELECTRICAL-Final 11/8/2024 Approved GEVORK IPCHYAN
Final 11/8/2024 OK to Issue CofO GEVORK IPCHYAN
Green Building Final 11/8/2024 Approved GEVORK IPCHYAN
HVAC-Final 11/8/2024 Approved GEVORK IPCHYAN
PLUMBING-Final 11/8/2024 Approved GEVORK IPCHYAN