9016 S WALL ST 90003
Certificate Information: 9016 S WALL ST 90003
- Application / Permit
- 24014-20000-01907
- Plan Check / Job No.
- B24VN06319
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan CONVERT EXISTING DETACHED 1-CAR GARAGE TO ADU WITH ADDITION PER ORDINANCE
- Permit Issued
- Issued on 6/26/2024
- Issuing Office
- Current Status
- CofO Issued on 11/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/10/2024 | MINA HABILI |
| Corrections Issued | 5/10/2024 | MINA HABILI |
| Applicant returned to address corrections | 6/3/2024 | KELVIN CHUONG |
| Applicant returned to address corrections | 6/11/2024 | KELVIN CHUONG |
| Plan Check Approved | 6/16/2024 | MINA HABILI |
| Issued | 6/26/2024 | APPLICANT |
| CofO in Progress | 11/5/2025 | JOHN QUINTANILLA |
| Permit Finaled | 11/9/2025 | DEROLD HAUFF |
| CofO Issued | 11/9/2025 | DEROLD HAUFF |
| Permit Finaled | 11/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/23/2024 | AMBER CAMPBELL |
| Roof/Waste drainage to street | Cleared | 5/23/2024 | AMBER CAMPBELL |
| Eng Process Fee Ord 176,300 | Cleared | 5/30/2024 | AMBER CAMPBELL |
| Sewer availability | Cleared | 6/3/2024 | DAVID LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vo,, Tung Thanh; Lic. No.: C69546 | 11122 BIXLER CIRCLE GARDEN GROVE, CA 92840 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/18/2024 | Approved | MICHAEL LEWIS |
| Sewer | 11/1/2024 | Corrections Issued | MICHAEL LEWIS |
| Underground Mechanical | 11/1/2024 | Approved | MICHAEL LEWIS |
| Sewer | 11/21/2024 | No Access for Inspection | MICHAEL LEWIS |
| Sewer | 12/5/2024 | Partial Approval | ANTHONY RAMOS |
| Footing/Foundation/Slab | 12/12/2024 | Corrections Issued | JOSE MACIAS |
| Deputy Wood Construction | 1/31/2025 | Conditional Approval | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2025 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 5/30/2025 | Corrections Issued | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 5/30/2025 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 5/30/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 6/17/2025 | Approved | JOHN QUINTANILLA |
| HVAC-Rough | 6/17/2025 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 6/17/2025 | Approved | JOHN QUINTANILLA |
| Wood Frame | 6/20/2025 | No Access for Inspection | LUIS CASTRO |
| Underground Mechanical | 6/23/2025 | Approved | JOHN QUINTANILLA |
| Wood Frame | 6/23/2025 | Corrections Issued | JOHN QUINTANILLA |
| Shower Pan | 6/26/2025 | Approved | JOHN QUINTANILLA |
| Wood Frame | 6/26/2025 | Approved | JOHN QUINTANILLA |
| Insulation | 6/27/2025 | Approved | JOHN QUINTANILLA |
| Drywall Nailing | 7/7/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 7/10/2025 | Approved | RONNIE MEDINA |
| Pre-Inspection | 9/25/2025 | Partial Inspection | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 10/10/2025 | Approved | JOHN QUINTANILLA |
| Final | 10/10/2025 | Corrections Issued | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 10/10/2025 | Approved | JOHN QUINTANILLA |
| Green Building Final | 10/10/2025 | Approved | JOHN QUINTANILLA |
| Green Building Rough | 10/10/2025 | Approved | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 10/10/2025 | SGSOV Approved | JOHN QUINTANILLA |
| Smoke Detectors | 10/10/2025 | Approved | JOHN QUINTANILLA |
| Final | 10/16/2025 | OK to Issue CofO | JOHN QUINTANILLA |