100 S LA JOLLA AVE 90048

Certificate Information: 100 S LA JOLLA AVE 90048

Application / Permit
24014-20000-01903
Plan Check / Job No.
B24VN06309
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL THORUGH OUT, 45 SF NORTH SIDE ADDITION, 351 SF NORHT-EAST SIDE ADDITION, AND 25 SF SOUTH SIDE ADDITION TO (E) SFD. ALL WORK PER ENG.
Permit Issued
Issued on 6/20/2024
Issuing Office
Valley
Current Status
CofO Issued on 2/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/7/2024 APPLICANT
Assigned to Plan Check Engineer 5/13/2024 JESSE ARELLANO
Corrections Issued 5/13/2024 JESSE ARELLANO
Building Plans Picked Up 5/15/2024 APPLICANT
Plan Check Approved 6/18/2024 ARAMIK SHAHMIRZAIAN
Issued 6/20/2024 APPLICANT
CofO in Progress 2/1/2025 MICHAEL PELHAM
CofO Issued 2/1/2025 RICHARD STEINBACH
Permit Finaled 2/1/2025 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/18/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 6/13/2024 JUSTIN BICOL
Sewer availability Cleared 6/13/2024 JUSTIN BICOL

Contact Information

Contractor V S Construction Inc; Lic. No.: 991805-B 7222 HINDS AVE      NORTH HOLLYWOOD, CA 91605
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/12/2024 No Access for Inspection MEL KHACHATOURIAN
Footing/Foundation/Slab 7/12/2024 Approved MEL KHACHATOURIAN
METHANE-Barrier 7/12/2024 Approved MEL KHACHATOURIAN
METHANE-Subgrade 7/12/2024 Approved MEL KHACHATOURIAN
PLUMBING-Rough 7/23/2024 Partial Approval SEAN HAUPT
Wood Frame 7/23/2024 Partial Approval SEAN HAUPT
Insulation 7/24/2024 Partial Approval MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 7/25/2024 Partial Approval MEL KHACHATOURIAN
Deputy Wood Construction 7/29/2024 Partial Approval MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 7/29/2024 Partial Approval MEL KHACHATOURIAN
HVAC-Rough 8/30/2024 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 8/30/2024 Not Ready for Inspection MEL KHACHATOURIAN
Special/Order Compliance 8/30/2024 Corrections Issued MEL KHACHATOURIAN
ELECTRICAL-Rough 9/4/2024 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 9/4/2024 Approved ARAM AVEDISIAN
HVAC-Rough 9/5/2024 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 9/5/2024 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 9/10/2024 Partial Approval ARAM AVEDISIAN
Green Building Rough 9/10/2024 Not Ready for Inspection ARAM AVEDISIAN
METHANE-Rough 9/10/2024 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 9/16/2024 Approved ARAM AVEDISIAN
Green Building Rough 9/16/2024 Approved ARAM AVEDISIAN
HVAC-Rough 9/16/2024 Approved ARAM AVEDISIAN
Insulation 9/16/2024 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 9/16/2024 Partial Approval ARAM AVEDISIAN
Drywall Nailing 9/23/2024 Approved ARAM AVEDISIAN
Shower Pan 9/26/2024 Partial Approval ARAM AVEDISIAN
Shower Pan 9/30/2024 Approved SEAN HAUPT
Interior/Exterior Lathing 10/4/2024 Approved MEL KHACHATOURIAN
Final 1/22/2025 Corrections Issued ARAM AVEDISIAN
Green Building Final 1/22/2025 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 1/22/2025 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 1/22/2025 Approved ARAM AVEDISIAN
Final 1/24/2025 Partial Approval MEL KHACHATOURIAN
Final 1/29/2025 OK to Issue CofO MEL KHACHATOURIAN