100 S LA JOLLA AVE 90048
Certificate Information: 100 S LA JOLLA AVE 90048
- Application / Permit
- 24014-20000-01903
- Plan Check / Job No.
- B24VN06309
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL THORUGH OUT, 45 SF NORTH SIDE ADDITION, 351 SF NORHT-EAST SIDE ADDITION, AND 25 SF SOUTH SIDE ADDITION TO (E) SFD. ALL WORK PER ENG.
- Permit Issued
- Issued on 6/20/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2024 | JESSE ARELLANO |
| Corrections Issued | 5/13/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 5/15/2024 | APPLICANT |
| Plan Check Approved | 6/18/2024 | ARAMIK SHAHMIRZAIAN |
| Issued | 6/20/2024 | APPLICANT |
| CofO in Progress | 2/1/2025 | MICHAEL PELHAM |
| CofO Issued | 2/1/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/1/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/18/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 6/13/2024 | JUSTIN BICOL |
Contact Information
| Contractor | V S Construction Inc; Lic. No.: 991805-B | 7222 HINDS AVE NORTH HOLLYWOOD, CA 91605 |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/12/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 7/12/2024 | Approved | MEL KHACHATOURIAN |
| METHANE-Barrier | 7/12/2024 | Approved | MEL KHACHATOURIAN |
| METHANE-Subgrade | 7/12/2024 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 7/23/2024 | Partial Approval | SEAN HAUPT |
| Wood Frame | 7/23/2024 | Partial Approval | SEAN HAUPT |
| Insulation | 7/24/2024 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2024 | Partial Approval | MEL KHACHATOURIAN |
| Deputy Wood Construction | 7/29/2024 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2024 | Partial Approval | MEL KHACHATOURIAN |
| HVAC-Rough | 8/30/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 8/30/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Special/Order Compliance | 8/30/2024 | Corrections Issued | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 9/4/2024 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 9/4/2024 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 9/5/2024 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 9/5/2024 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 9/10/2024 | Partial Approval | ARAM AVEDISIAN |
| Green Building Rough | 9/10/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| METHANE-Rough | 9/10/2024 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 9/16/2024 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 9/16/2024 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 9/16/2024 | Approved | ARAM AVEDISIAN |
| Insulation | 9/16/2024 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 9/16/2024 | Partial Approval | ARAM AVEDISIAN |
| Drywall Nailing | 9/23/2024 | Approved | ARAM AVEDISIAN |
| Shower Pan | 9/26/2024 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 9/30/2024 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 10/4/2024 | Approved | MEL KHACHATOURIAN |
| Final | 1/22/2025 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 1/22/2025 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 1/22/2025 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 1/22/2025 | Approved | ARAM AVEDISIAN |
| Final | 1/24/2025 | Partial Approval | MEL KHACHATOURIAN |
| Final | 1/29/2025 | OK to Issue CofO | MEL KHACHATOURIAN |