13267 W SUNBURST ST 91331
Certificate Information: 13267 W SUNBURST ST 91331
- Application / Permit
- 24014-20000-01893
- Plan Check / Job No.
- B24VN06289
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Bathroom addition
- Permit Issued
- Issued on 12/3/2024
- Issuing Office
- Current Status
- CofO Issued on 5/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/7/2024 | NEHEMIAS RAMOS |
| Corrections Issued | 5/7/2024 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 8/13/2024 | NEHEMIAS RAMOS |
| Plan Check Approved | 9/4/2024 | NEHEMIAS RAMOS |
| Issued | 12/3/2024 | APPLICANT |
| CofO in Progress | 5/8/2025 | MICHEL ABAJAN |
| Permit Finaled | 5/15/2025 | RUBEN SALAS |
| CofO Issued | 5/15/2025 | RUBEN SALAS |
| Permit Finaled | 5/15/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/6/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/16/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Artner West Construction Inc; Lic. No.: 446733-B | , |
| Engineer | Reith,, David Lee; Lic. No.: NA72122 | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/18/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 12/24/2024 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2025 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 2/14/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 2/14/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 2/14/2025 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 2/14/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 2/14/2025 | Approved | MICHEL ABAJAN |
| Insulation | 2/24/2025 | Approved | MICHEL ABAJAN |
| Shower Pan | 2/24/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 4/29/2025 | Approved | MICHEL ABAJAN |
| Final | 4/29/2025 | Corrections Issued | MICHEL ABAJAN |
| HVAC-Final | 4/29/2025 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 4/29/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 4/29/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 4/29/2025 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 4/29/2025 | Approved | MICHEL ABAJAN |
| Final | 5/7/2025 | OK to Issue CofO | MICHEL ABAJAN |