10137 SALOMA AVE 91345

Certificate Information: 10137 SALOMA AVE 91345

Application / Permit
24014-20000-01892
Plan Check / Job No.
B24VN06286
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: NEW ADDITION TO EXISTING ACESSORY DWELLING UNIT PER LAMC SEC. 12.22A33.(c) AND(d).
Permit Issued
Issued on 10/2/2024
Issuing Office
Current Status
CofO Issued on 5/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/7/2024 APPLICANT
Assigned to Plan Check Engineer 5/10/2024 PINANK PATEL
Corrections Issued 5/10/2024 PINANK PATEL
Plan Check Approved 10/2/2024 PINANK PATEL
Issued 10/2/2024 APPLICANT
CofO in Progress 5/16/2025 RAUL OLAGI
Permit Finaled 5/27/2025 RUBEN SALAS
CofO Issued 5/27/2025 RUBEN SALAS
Permit Finaled 5/27/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/16/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 5/16/2024 BIAINA HARITUNIAN
Sewer availability Cleared 5/16/2024 BIAINA HARITUNIAN
Construction near power lines Cleared 10/2/2024 TINA MIRANDA

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/23/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 10/29/2024 Corrections Issued GREGG CUMMINGS
Footing/Foundation/Slab 11/14/2024 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/17/2024 Partial Approval JENNIFER RABUCHIN
Insulation 12/17/2024 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 12/20/2024 Corrections Issued MISAEL ESPARZA
Wood Frame 2/28/2025 Not Ready for Inspection ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 3/4/2025 Partial Approval JUAN VALENZUELA
ELECTRICAL-Rough 3/19/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 3/19/2025 Approved JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 4/1/2025 Approved JENNIFER RABUCHIN
Insulation 4/1/2025 Conditional Approval JENNIFER RABUCHIN
Drywall Nailing 4/7/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/12/2025 Approved RAUL OLAGI
Final 5/12/2025 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 5/12/2025 Approved RAUL OLAGI
Green Building Final 5/12/2025 Approved RAUL OLAGI
Green Building Rough 5/12/2025 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 5/12/2025 SGSOV Approved RAUL OLAGI
Smoke Detectors 5/12/2025 Approved RAUL OLAGI
Final 5/16/2025 OK to Issue CofO RAUL OLAGI