7307 N FARMDALE AVE 91605

Certificate Information: 7307 N FARMDALE AVE 91605

Application / Permit
24014-20000-01880
Plan Check / Job No.
B24VN06220
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
***ePlan*** Bathroom addition to the front side of (e) 1-story SFD per WFPP
Permit Issued
Issued on 6/20/2024
Issuing Office
Current Status
CofO Issued on 4/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/6/2024 APPLICANT
Assigned to Plan Check Engineer 5/7/2024 ZENA HADDIS
Corrections Issued 5/7/2024 ZENA HADDIS
Applicant returned to address corrections 5/18/2024 ZENA HADDIS
Plan Check Approved 6/15/2024 REZA HAGHIGHAT
Issued 6/20/2024 APPLICANT
CofO in Progress 3/13/2025 ROBERTO PALACIOS-LOPEZ
Permit Finaled 4/17/2025 RUBEN SALAS
CofO Issued 4/17/2025 RUBEN SALAS
Permit Finaled 4/17/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/25/2024 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 5/28/2024 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/24/2024 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 10/9/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 10/9/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 10/15/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Insulation 10/15/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 12/11/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 12/11/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 12/11/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Final 12/11/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Rough 12/11/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Final 12/11/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 12/11/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Service/Power Release 12/11/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Smoke Detectors 12/11/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 1/7/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 1/7/2025 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 1/7/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 1/7/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Rough 1/14/2025 Approved JOSE AVILA
PLUMBING-Rough 1/14/2025 Approved JOSE AVILA
Shower Pan 1/14/2025 Not Ready for Inspection JOSE AVILA
Insulation 1/29/2025 Approved JACK KARGODORIAN
Interior/Exterior Lathing 1/29/2025 Partial Approval JACK KARGODORIAN
Shower Pan 1/29/2025 Not Ready for Inspection JACK KARGODORIAN
BUILDING-Rough-Frame 2/4/2025 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 2/4/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 2/4/2025 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 2/4/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 2/25/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Final 2/25/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Smoke Detectors 2/25/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 2/27/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 3/13/2025 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Green Building Final 3/13/2025 Approved ROBERTO PALACIOS-LOPEZ
Smoke Detectors 3/13/2025 Approved ROBERTO PALACIOS-LOPEZ