- eplan: convert existing detached 1 story garge with addtion to ADU per WFPP (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
- Permit Issued
- Issued on 12/27/2024
- Issuing Office
- Current Status
- CofO Issued on 1/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/5/2024 | AUNG SOE |
| Corrections Issued | 6/7/2024 | AUNG SOE |
| Applicant returned to address corrections | 11/9/2024 | AUNG SOE |
| Applicant returned to address corrections | 11/22/2024 | AUNG SOE |
| Plan Check Approved | 11/24/2024 | AUNG SOE |
| Issued | 12/27/2024 | APPLICANT |
| CofO in Progress | 12/16/2025 | NICHOLAS TROWBRIDGE |
| Permit Finaled | 1/13/2026 | RUBEN SALAS |
| CofO Issued | 1/13/2026 | RUBEN SALAS |
| Permit Finaled | 1/13/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/14/2024 | GERMAN RODRIGUEZ MENDOZA |
| Address approval | Cleared | 6/15/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 6/15/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/18/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/18/2024 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 10/4/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/4/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/30/2025 | Partial Approval | WILLIAM WREN |
| Footing/Foundation/Slab | 5/7/2025 | Corrections Issued | WILLIAM WREN |
| Deputy Drilled-In Anchors | 5/13/2025 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 5/14/2025 | Partial Approval | WILLIAM WREN |
| PLUMBING-Rough | 6/25/2025 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2025 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 7/2/2025 | Partial Approval | MICHEL ABAJAN |
| Underground Mechanical | 7/2/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 7/22/2025 | Not Ready for Inspection | WILLIAM WREN |
| ELECTRICAL-Rough | 7/22/2025 | Approved | WILLIAM WREN |
| Green Building Rough | 7/22/2025 | Not Ready for Inspection | WILLIAM WREN |
| HVAC-Rough | 7/22/2025 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 7/24/2025 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2025 | Partial Approval | WILLIAM WREN |
| Green Building Rough | 7/24/2025 | Approved | WILLIAM WREN |
| Wood Frame | 7/24/2025 | Not Ready for Inspection | WILLIAM WREN |
| Interior/Exterior Lathing | 7/30/2025 | Partial Approval | WILLIAM WREN |
| Insulation | 8/1/2025 | Corrections Issued | JOAQUIN GREENOUGH |
| Insulation | 8/5/2025 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2025 | Approved | WILLIAM WREN |
| Shower Pan | 8/8/2025 | Approved | WILLIAM WREN |
| Drywall Nailing | 8/18/2025 | Approved | WILLIAM WREN |
| Underground Mechanical | 8/18/2025 | Approved | WILLIAM WREN |
| Final | 11/10/2025 | Corrections Issued | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 11/10/2025 | Approved | KEVIN BERBERYAN |
| Green Building Final | 11/10/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 11/10/2025 | SGSOV Not Ready | KEVIN BERBERYAN |
| Smoke Detectors | 11/10/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 12/1/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Final | 12/1/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 12/1/2025 | SGSOV Not Ready | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 12/1/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Final | 12/8/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Final | 12/8/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Green Building Final | 12/8/2025 | Approved | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 12/8/2025 | SGSOV Approved | NICHOLAS TROWBRIDGE |
| Service/Power Release | 12/8/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Final | 12/15/2025 | OK to Issue CofO | NICHOLAS TROWBRIDGE |