8130 W KYLE ST 91040

Certificate Information: 8130 W KYLE ST 91040

Application / Permit
24014-20000-01874
Plan Check / Job No.
B24VN06196
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: convert existing detached 1 story garge with addtion to ADU per WFPP (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
Permit Issued
Issued on 12/27/2024
Issuing Office
Current Status
CofO Issued on 1/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/2/2024 APPLICANT
Assigned to Plan Check Engineer 6/5/2024 AUNG SOE
Corrections Issued 6/7/2024 AUNG SOE
Applicant returned to address corrections 11/9/2024 AUNG SOE
Applicant returned to address corrections 11/22/2024 AUNG SOE
Plan Check Approved 11/24/2024 AUNG SOE
Issued 12/27/2024 APPLICANT
CofO in Progress 12/16/2025 NICHOLAS TROWBRIDGE
Permit Finaled 1/13/2026 RUBEN SALAS
CofO Issued 1/13/2026 RUBEN SALAS
Permit Finaled 1/13/2026 RUBEN SALAS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/14/2024 GERMAN RODRIGUEZ MENDOZA
Address approval Cleared 6/15/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 6/15/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/18/2024 CARLOS AGUILERA
Sewer availability Cleared 6/18/2024 CARLOS AGUILERA
Construction near power lines Cleared 10/4/2024 RIDWAN HARDY
Construction within easement Cleared 10/4/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/30/2025 Partial Approval WILLIAM WREN
Footing/Foundation/Slab 5/7/2025 Corrections Issued WILLIAM WREN
Deputy Drilled-In Anchors 5/13/2025 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 5/14/2025 Partial Approval WILLIAM WREN
PLUMBING-Rough 6/25/2025 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 7/2/2025 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 7/2/2025 Partial Approval MICHEL ABAJAN
Underground Mechanical 7/2/2025 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 7/22/2025 Not Ready for Inspection WILLIAM WREN
ELECTRICAL-Rough 7/22/2025 Approved WILLIAM WREN
Green Building Rough 7/22/2025 Not Ready for Inspection WILLIAM WREN
HVAC-Rough 7/22/2025 Approved WILLIAM WREN
BUILDING-Rough-Frame 7/24/2025 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 7/24/2025 Partial Approval WILLIAM WREN
Green Building Rough 7/24/2025 Approved WILLIAM WREN
Wood Frame 7/24/2025 Not Ready for Inspection WILLIAM WREN
Interior/Exterior Lathing 7/30/2025 Partial Approval WILLIAM WREN
Insulation 8/1/2025 Corrections Issued JOAQUIN GREENOUGH
Insulation 8/5/2025 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 8/8/2025 Approved WILLIAM WREN
Shower Pan 8/8/2025 Approved WILLIAM WREN
Drywall Nailing 8/18/2025 Approved WILLIAM WREN
Underground Mechanical 8/18/2025 Approved WILLIAM WREN
Final 11/10/2025 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 11/10/2025 Approved KEVIN BERBERYAN
Green Building Final 11/10/2025 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 11/10/2025 SGSOV Not Ready KEVIN BERBERYAN
Smoke Detectors 11/10/2025 Not Ready for Inspection KEVIN BERBERYAN
Final 12/1/2025 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Final 12/1/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 12/1/2025 SGSOV Not Ready NICHOLAS TROWBRIDGE
Smoke Detectors 12/1/2025 Approved NICHOLAS TROWBRIDGE
ELECTRICAL-Final 12/8/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Final 12/8/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Green Building Final 12/8/2025 Approved NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 12/8/2025 SGSOV Approved NICHOLAS TROWBRIDGE
Service/Power Release 12/8/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Final 12/15/2025 OK to Issue CofO NICHOLAS TROWBRIDGE