5746 N ALLOTT AVE 91401

Certificate Information: 5746 N ALLOTT AVE 91401

Application / Permit
24014-20000-01863
Plan Check / Job No.
B24VN06177
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
IRREG SHAPED ADDITION TO AND CONVERT DETACHED GARAGE / STORAGE ROOM TO ACCESSORY DWELLING UNIT (736 SQ FT) PER LAMC 12.22 A.33(c) and (d). ALL WORK PER ENGINEERING
Permit Issued
Issued on 10/21/2024
Issuing Office
Current Status
CofO Issued on 11/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/6/2024 APPLICANT
Assigned to Plan Check Engineer 5/10/2024 JEROME MAGAT PALMA
Corrections Issued 5/11/2024 JEROME MAGAT PALMA
Building Plans Picked Up 5/15/2024 APPLICANT
Issued 10/21/2024 APPLICANT
CofO in Progress 11/3/2025 RYAN SALAZAR
Permit Finaled 11/13/2025 RUBEN SALAS
CofO Issued 11/13/2025 RUBEN SALAS
Permit Finaled 11/13/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/20/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 5/20/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/21/2024 CARLOS AGUILERA
Sewer availability Cleared 5/21/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/2/2025 Partial Approval RYAN SALAZAR
PLUMBING-Rough 5/2/2025 Partial Approval RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 5/7/2025 Approved RYAN SALAZAR
Deputy Reinf. Concrete 5/13/2025 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 5/14/2025 Approved RYAN SALAZAR
Sewer 5/29/2025 Approved RYAN SALAZAR
Deputy Wood Construction 5/30/2025 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 6/3/2025 Approved RYAN SALAZAR
ELECTRICAL-Rough 6/9/2025 Conditional Approval MISAEL ESPARZA
HVAC-Rough 6/9/2025 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 6/20/2025 Approved RYAN SALAZAR
HVAC-Rough 6/20/2025 Approved RYAN SALAZAR
PLUMBING-Rough 6/20/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 7/29/2025 Partial Approval LOUIS ESCOTO
Shower Pan 7/29/2025 Not Ready for Inspection LOUIS ESCOTO
BUILDING-Rough-Frame 8/1/2025 Conditional Approval NICHOLAS TROWBRIDGE
Green Building Rough 8/1/2025 Approved NICHOLAS TROWBRIDGE
Shower Pan 8/1/2025 Approved NICHOLAS TROWBRIDGE
Wood Frame 8/1/2025 Conditional Approval NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 8/5/2025 Approved RYAN SALAZAR
Insulation 8/8/2025 Approved RYAN SALAZAR
Drywall Nailing 8/14/2025 Approved RYAN SALAZAR
ELECTRICAL-Final 10/24/2025 Approved RYAN SALAZAR
Final 10/24/2025 Corrections Issued RYAN SALAZAR
Gas Test 10/24/2025 Approved RYAN SALAZAR
Green Building Final 10/24/2025 Approved RYAN SALAZAR
Grounding or Bonding 10/24/2025 Approved RYAN SALAZAR
HVAC-Final 10/24/2025 Approved RYAN SALAZAR
PLUMBING-Final 10/24/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 10/24/2025 SGSOV Approved RYAN SALAZAR
Service/Power Release 10/24/2025 Not Ready for Inspection RYAN SALAZAR
Smoke Detectors 10/24/2025 Approved RYAN SALAZAR
Deputy Drilled-In Anchors 11/3/2025 Conditional Approval RYAN SALAZAR
Final 11/3/2025 OK to Issue CofO RYAN SALAZAR
Service/Power Release 11/3/2025 Approved RYAN SALAZAR