5746 N ALLOTT AVE 91401
Certificate Information: 5746 N ALLOTT AVE 91401
- Application / Permit
- 24014-20000-01863
- Plan Check / Job No.
- B24VN06177
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- IRREG SHAPED ADDITION TO AND CONVERT DETACHED GARAGE / STORAGE ROOM TO ACCESSORY DWELLING UNIT (736 SQ FT) PER LAMC 12.22 A.33(c) and (d). ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 10/21/2024
- Issuing Office
- Current Status
- CofO Issued on 11/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/10/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 5/11/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 5/15/2024 | APPLICANT |
| Issued | 10/21/2024 | APPLICANT |
| CofO in Progress | 11/3/2025 | RYAN SALAZAR |
| Permit Finaled | 11/13/2025 | RUBEN SALAS |
| CofO Issued | 11/13/2025 | RUBEN SALAS |
| Permit Finaled | 11/13/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/20/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 5/20/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/21/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/21/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/2/2025 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 5/2/2025 | Partial Approval | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 5/7/2025 | Approved | RYAN SALAZAR |
| Deputy Reinf. Concrete | 5/13/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 5/14/2025 | Approved | RYAN SALAZAR |
| Sewer | 5/29/2025 | Approved | RYAN SALAZAR |
| Deputy Wood Construction | 5/30/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 6/9/2025 | Conditional Approval | MISAEL ESPARZA |
| HVAC-Rough | 6/9/2025 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 6/20/2025 | Approved | RYAN SALAZAR |
| HVAC-Rough | 6/20/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 6/20/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 7/29/2025 | Partial Approval | LOUIS ESCOTO |
| Shower Pan | 7/29/2025 | Not Ready for Inspection | LOUIS ESCOTO |
| BUILDING-Rough-Frame | 8/1/2025 | Conditional Approval | NICHOLAS TROWBRIDGE |
| Green Building Rough | 8/1/2025 | Approved | NICHOLAS TROWBRIDGE |
| Shower Pan | 8/1/2025 | Approved | NICHOLAS TROWBRIDGE |
| Wood Frame | 8/1/2025 | Conditional Approval | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 8/5/2025 | Approved | RYAN SALAZAR |
| Insulation | 8/8/2025 | Approved | RYAN SALAZAR |
| Drywall Nailing | 8/14/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 10/24/2025 | Approved | RYAN SALAZAR |
| Final | 10/24/2025 | Corrections Issued | RYAN SALAZAR |
| Gas Test | 10/24/2025 | Approved | RYAN SALAZAR |
| Green Building Final | 10/24/2025 | Approved | RYAN SALAZAR |
| Grounding or Bonding | 10/24/2025 | Approved | RYAN SALAZAR |
| HVAC-Final | 10/24/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 10/24/2025 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 10/24/2025 | SGSOV Approved | RYAN SALAZAR |
| Service/Power Release | 10/24/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Smoke Detectors | 10/24/2025 | Approved | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 11/3/2025 | Conditional Approval | RYAN SALAZAR |
| Final | 11/3/2025 | OK to Issue CofO | RYAN SALAZAR |
| Service/Power Release | 11/3/2025 | Approved | RYAN SALAZAR |