640 W 95TH ST 90044
Certificate Information: 640 W 95TH ST 90044
- Application / Permit
- 24014-20000-01861
- Plan Check / Job No.
- B24VN06175
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
- Permit Issued
- Issued on 7/18/2024
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 8/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/10/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 5/14/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 5/15/2024 | APPLICANT |
| Plan Check Approved | 6/6/2024 | ISIS ARGUETA |
| Issued | 7/18/2024 | APPLICANT |
| CofO in Progress | 7/31/2025 | BEN MOLSTAD |
| Permit Finaled | 8/1/2025 | ANSON MAGLASANG |
| CofO Issued | 8/1/2025 | ANSON MAGLASANG |
| Permit Finaled | 8/1/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 6/1/2024 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 6/1/2024 | ERIK BEASLEY |
| Sewer availability | Cleared | 6/1/2024 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2024 | ERIK BEASLEY |
Contact Information
| Architect | Miller,, Michael; Lic. No.: C26956 | 12756 MITCHELL AVE LOS ANGELES, CA 90066 |
| Contractor | Owner-Builder | , |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/21/2024 | Approved | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 8/22/2024 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2024 | Partial Approval | BEN MOLSTAD |
| Wood Frame | 11/13/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Wood Frame | 12/24/2024 | Partial Approval | JOSEPH MCGARRY |
| Insulation | 1/7/2025 | Approved | BEN MOLSTAD |
| Wood Frame | 1/7/2025 | Approved | BEN MOLSTAD |
| Drywall Nailing | 1/13/2025 | Corrections Issued | BEN MOLSTAD |
| Drywall Nailing | 1/15/2025 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 1/28/2025 | Approved | BEN MOLSTAD |
| Pre-Inspection | 1/28/2025 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 7/8/2025 | Approved | BEN MOLSTAD |
| Final | 7/8/2025 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 7/8/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Rough | 7/8/2025 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 7/8/2025 | SGSOV Approved | BEN MOLSTAD |
| Smoke Detectors | 7/8/2025 | Approved | BEN MOLSTAD |
| Final | 7/28/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Final | 7/28/2025 | Approved | BEN MOLSTAD |
| Final | 7/30/2025 | OK to Issue CofO | BEN MOLSTAD |