22141 W CANTLAY ST 91303

Certificate Information: 22141 W CANTLAY ST 91303

Application / Permit
24014-20000-01810
Plan Check / Job No.
B24VN06019
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. Convert existing garage (528 sf) with addition (270 sf) to new detached ADU (798 sf) per state law
Permit Issued
Issued on 1/18/2025
Issuing Office
Current Status
CofO Issued on 4/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/2/2024 APPLICANT
Assigned to Plan Check Engineer 5/7/2024 KHUONG TRUONG
Corrections Issued 5/8/2024 KHUONG TRUONG
Applicant returned to address corrections 10/2/2024 TSE MING HUANG
Plan Check Approved 10/22/2024 ZAW HAN
Issued 1/18/2025 APPLICANT
CofO in Progress 1/29/2026 JEFFREY HARTLINE
Permit Finaled 4/4/2026 MICHAEL PELHAM
CofO Issued 4/4/2026 MICHAEL PELHAM
Permit Finaled 4/4/2026 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 7/22/2024 TAL SHEMEN
Roof/Waste drainage to street Cleared 7/22/2024 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 7/23/2024 TAL SHEMEN
Sewer availability Cleared 7/23/2024 TAL SHEMEN
Construction near power lines Cleared 9/13/2024 RIDWAN HARDY
Construction within easement Cleared 9/13/2024 RIDWAN HARDY

Contact Information

Contractor Sosa Remodeling & Construction; Lic. No.: 1036208-B 18757 LEADWELL ST      RESEDA, CA 91335
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/28/2025 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 2/25/2025 Conditional Approval CHRIS CHRISTENSEN
Special/Order Compliance 2/25/2025 Corrections Issued CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/6/2025 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 5/6/2025 Approved CHRIS CHRISTENSEN
Green Building Rough 5/6/2025 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 5/6/2025 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/14/2025 Approved CHRIS CHRISTENSEN
Green Building Rough 5/14/2025 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 5/14/2025 Partial Approval CHRIS CHRISTENSEN
Insulation 6/11/2025 Approved CHRIS CHRISTENSEN
Drywall Nailing 6/24/2025 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 9/23/2025 Partial Approval JEFFREY HARTLINE
ELECTRICAL-Final 1/15/2026 Approved CHRIS CHRISTENSEN
Final 1/15/2026 Corrections Issued CHRIS CHRISTENSEN
Footing/Foundation/Slab 1/15/2026 Approved CHRIS CHRISTENSEN
Green Building Final 1/15/2026 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Final 1/15/2026 Approved CHRIS CHRISTENSEN
PLUMBING-Final 1/15/2026 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 1/15/2026 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 1/15/2026 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 1/29/2026 Approved JEFFREY HARTLINE
Final 1/29/2026 OK to Issue CofO JEFFREY HARTLINE
Green Building Final 1/29/2026 Approved JEFFREY HARTLINE
HVAC-Final 1/29/2026 Approved JEFFREY HARTLINE
PLUMBING-Final 1/29/2026 Approved JEFFREY HARTLINE
Service/Power Release 1/29/2026 Approved JEFFREY HARTLINE