6528 N BUFFALO AVE 91401
Certificate Information: 6528 N BUFFALO AVE 91401
- Application / Permit
- 24014-20000-01794
- Plan Check / Job No.
- B24VN05954
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18'2" X 20'2" DETACHED GARAGE AND (N) 25'7" X 30' ADDITION TO (N) ACCESSORY DWELLING UNIT (1071 SF) PER LAMC 12.22 A.33(c) AND (d). (N) 14'5" X 22'6" STORAGE ATTACHED TO ADU. WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 8/6/2024
- Issuing Office
- Metro
- Current Status
- CofO in Progress on 3/5/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/7/2024 | JESSE ARELLANO |
| Corrections Issued | 5/8/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 5/10/2024 | APPLICANT |
| Plan Check Approved | 8/5/2024 | MADISON O'DELL |
| Issued | 8/6/2024 | APPLICANT |
| CofO in Progress | 3/5/2026 | WAYNE REGESTER |
Permit Application Clearance Information
| Construction near power lines | Cleared | 7/29/2024 | WALTER RAMIREZ |
| Address approval | Cleared | 7/30/2024 | CARLOS RAMIREZ |
| Roof/Waste drainage to street | Cleared | 7/30/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 8/2/2024 | CARLOS RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/8/2024 | Partial Approval | KEVIN BERBERYAN |
| Underground Mechanical | 8/8/2024 | Approved | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 8/26/2024 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 10/31/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Green Building Rough | 10/31/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 12/12/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2024 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Rough | 12/12/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| HVAC-Rough | 12/12/2024 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 12/12/2024 | Corrections Issued | GAREN HAYRAPETYAN |
| Underground Mechanical | 3/4/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Wood Frame | 3/4/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 3/5/2025 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 3/5/2025 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 3/18/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 3/18/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Insulation | 3/27/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Insulation | 4/1/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 4/1/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Drywall Nailing | 4/11/2025 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 4/11/2025 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/21/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 9/29/2025 | Approved | WAYNE REGESTER |
| Final | 9/29/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Final | 9/29/2025 | Approved | WAYNE REGESTER |
| Green Building Rough | 9/29/2025 | Approved | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 9/29/2025 | SGSOV Not Ready | WAYNE REGESTER |
| Smoke Detectors | 9/29/2025 | Approved | WAYNE REGESTER |
| Final | 2/12/2026 | Corrections Issued | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 2/12/2026 | SGSOV Approved | DAVID ANDERSON |
| Final | 3/2/2026 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Final | 3/5/2026 | Approved | WAYNE REGESTER |
| Final | 3/5/2026 | OK to Issue CofO | WAYNE REGESTER |
| Green Building Final | 3/5/2026 | Approved | WAYNE REGESTER |
| HVAC-Final | 3/5/2026 | Approved | WAYNE REGESTER |
| PLUMBING-Final | 3/5/2026 | Approved | WAYNE REGESTER |