6646 N PEACH AVE 91406
Certificate Information: 6646 N PEACH AVE 91406
- Application / Permit
- 24014-20000-01773
- Plan Check / Job No.
- B24VN04853
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 30' X 22'-2" TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT
- Permit Issued
- Issued on 6/11/2025
- Issuing Office
- Current Status
- CofO Issued on 4/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2024 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 5/15/2024 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 5/29/2024 | STEVEN KIM |
| Applicant returned to address corrections | 10/16/2024 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 5/20/2025 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 6/5/2025 | SEWADA ZADOORAN MILAGARDI |
| Issued | 6/11/2025 | APPLICANT |
| CofO in Progress | 2/27/2026 | VINCENT HANLEY |
| Permit Finaled | 4/3/2026 | RUBEN SALAS |
| Permit Finaled | 4/3/2026 | RUBEN SALAS |
| CofO Issued | 4/3/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/17/2024 | CARLOS RAMIREZ |
| Roof/Waste drainage to street | Cleared | 6/17/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/18/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 6/20/2024 | CARLOS RAMIREZ |
| Construction near power lines | Cleared | 7/22/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 7/22/2024 | RIDWAN HARDY |
| ZI | Cleared | 10/11/2024 | BRENNEN OBETO |
| ZI | Cleared | 5/27/2025 | ASHLEY RODARTE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/26/2025 | Partial Approval | RYAN SALAZAR |
| Footing/Foundation/Slab | 7/3/2025 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2025 | Corrections Issued | RYAN SALAZAR |
| Deputy Wood Construction | 7/17/2025 | Conditional Approval | JUAN VALENZUELA |
| Deputy Wood Construction | 8/4/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 8/19/2025 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 8/19/2025 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 8/27/2025 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2025 | Approved | RYAN SALAZAR |
| HVAC-Rough | 8/27/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 8/27/2025 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 9/2/2025 | Approved | RYAN SALAZAR |
| Green Building Rough | 9/2/2025 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 9/2/2025 | Approved | RYAN SALAZAR |
| Sewer | 9/26/2025 | Approved | RYAN SALAZAR |
| Insulation | 10/6/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 10/6/2025 | Approved | RYAN SALAZAR |
| Drywall Nailing | 10/14/2025 | Approved | RYAN SALAZAR |
| Underground Mechanical | 12/9/2025 | Approved | RYAN SALAZAR |
| Green Building Final | 2/5/2026 | No Access for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 2/5/2026 | SGSOV Not Ready | JAVIER RAMOS JR |
| Service/Power Release | 2/5/2026 | No Access for Inspection | JAVIER RAMOS JR |
| Smoke Detectors | 2/5/2026 | No Access for Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Final | 2/6/2026 | Approved | VINCENT HANLEY |
| Final | 2/6/2026 | Corrections Issued | VINCENT HANLEY |
| HVAC-Final | 2/6/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 2/6/2026 | Approved | VINCENT HANLEY |
| Final | 2/24/2026 | No Access for Inspection | MICHEL ABAJAN |
| Green Building Final | 2/24/2026 | No Access for Inspection | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 2/24/2026 | SGSOV Not Ready | MICHEL ABAJAN |
| Service/Power Release | 2/24/2026 | No Access for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 2/24/2026 | No Access for Inspection | MICHEL ABAJAN |
| Final | 2/26/2026 | OK to Issue CofO | VINCENT HANLEY |
| Green Building Final | 2/26/2026 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 2/26/2026 | SGSOV Not Required | VINCENT HANLEY |
| Service/Power Release | 2/26/2026 | Approved | VINCENT HANLEY |
| Smoke Detectors | 2/26/2026 | Approved | VINCENT HANLEY |