13330-13330 1/2 W AZTEC ST 91342

Certificate Information: 13330-13330 1/2 W AZTEC ST 91342

Application / Permit
24014-20000-01748
Plan Check / Job No.
B24VN05830
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE AND COVERED BREEZEWAY TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e). ADDITION TO SFD TO ENLARGE (E) BEDROOM AND ADD NEW BATHROOM.
Permit Issued
Issued on 2/13/2026
Issuing Office
Valley
Current Status
Issued on 2/13/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/29/2024 APPLICANT
Assigned to Plan Check Engineer 5/6/2024 JEROME MAGAT PALMA
Corrections Issued 5/8/2024 JEROME MAGAT PALMA
Building Plans Picked Up 5/13/2024 APPLICANT
Plan Check Approved 2/13/2026 GURUNATH NESARAJAH
Issued 2/13/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/15/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 5/15/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 5/15/2024 BIAINA HARITUNIAN
Sewer availability Cleared 5/15/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/19/2026 Corrections Issued KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 3/23/2026 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 3/23/2026 Partial Approval KEVIN BERBERYAN
Sewer 3/23/2026 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 3/24/2026 Approved JENNIFER RABUCHIN
Sewer 3/24/2026 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 4/6/2026 Partial Approval MICHEL ABAJAN
Green Building Rough 4/8/2026 Corrections Issued KEVIN BERBERYAN
Reinforced Concrete Frame 4/21/2026 Not Ready for Inspection NICHOLAS TROWBRIDGE
Reinforced Masonry Frame 4/21/2026 Not Ready for Inspection NICHOLAS TROWBRIDGE
Rough-Elec/Plmb/HVAC 4/21/2026 Corrections Issued NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 4/21/2026 SGSOV Not Ready NICHOLAS TROWBRIDGE
Wood Frame 4/21/2026 Not Ready for Inspection NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 4/30/2026 No Access for Inspection MISAEL ESPARZA
Green Building Rough 4/30/2026 No Access for Inspection MISAEL ESPARZA
Piling/Pier/Caisson 4/30/2026 No Access for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 4/30/2026 SGSOV Not Ready MISAEL ESPARZA
Wood Frame 4/30/2026 No Access for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 5/4/2026 Approved KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 5/4/2026 Approved KEVIN BERBERYAN
HVAC-Rough 5/4/2026 Not Ready for Inspection KEVIN BERBERYAN
BUILDING-Rough-Frame 6/1/2026 Approved Pending GreenApproval KEVIN BERBERYAN
Insulation 6/1/2026 Corrections Issued KEVIN BERBERYAN
Drywall Nailing 6/22/2026 Corrections Issued KEVIN BERBERYAN
Drywall Nailing 7/1/2026 Approved JOSE AVILA