4532 N WOODLEY AVE 91436

Certificate Information: 4532 N WOODLEY AVE 91436

Application / Permit
24014-20000-01726
Plan Check / Job No.
B24VN05712
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remove portion of the SFD on the East portion of the lot. Addition and remodel of irregular shaped single family dwelling with attached garage to new building footprint of 73' 1 1/2" x 89' 10". All work done per engineer.
Permit Issued
Issued on 7/10/2024
Issuing Office
Valley
Current Status
CofO in Progress on 5/12/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/25/2024 APPLICANT
Assigned to Plan Check Engineer 5/9/2024 NAREG ATARIAN
Corrections Issued 5/15/2024 NAREG ATARIAN
Quality Review Completed 5/20/2024 OMID HEDAYAT
Building Plans Picked Up 5/21/2024 APPLICANT
Applicant returned to address corrections 6/13/2024 NAREG ATARIAN
Plan Check Approved 7/1/2024 NAREG ATARIAN
Issued 7/10/2024 APPLICANT
CofO in Progress 5/12/2026 THOMAS FINNILA

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/1/2024 EDGAR ALCARAZ
Sewer availability Cleared 6/1/2024 EDGAR ALCARAZ
Miscellaneous Cleared 6/18/2024 ALEX VELA
Eng Process Fee Ord 176,300 Cleared 6/21/2024 CARLOS RAMIREZ
GPI Written Notices Cleared 7/1/2024 RUSSELL BONVOULOIR
Grading Pre-Inspection Cleared 7/1/2024 RUSSELL BONVOULOIR

Contact Information

Architect Gemigniani,, Richard Louis; Lic. No.: C18783 1816 HILLCREST AVENUE      GLENDALE, CA 91202
Contractor Brytin Construction; Lic. No.: 1065160-B 1140 AGNEW STREET      SIMI VALLEY, CA 93065

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/26/2024 Partial Inspection THOMAS FINNILA
Pre-Inspection 7/30/2024 Partial Inspection MORRIS JACKSON
Footing/Foundation/Slab 8/29/2024 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 9/4/2024 Approved JEFFREY HARTLINE
Piling/Pier/Caisson 9/17/2024 Partial Inspection THOMAS FINNILA
BUILDING-Rough-Frame 9/25/2024 Not Ready for Inspection ALEXANDER HANDY
Green Building Rough 9/25/2024 Not Ready for Inspection ALEXANDER HANDY
Sewer 9/26/2024 Partial Approval THOMAS FINNILA
Wood Frame 9/26/2024 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/30/2024 Partial Approval MORRIS JACKSON
Green Building Rough 9/30/2024 Not Ready for Inspection MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 10/24/2024 Partial Approval MORRIS JACKSON
Deputy Drilled-In Anchors 10/25/2024 Conditional Approval THOMAS FINNILA
HVAC-Rough 12/5/2024 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 12/5/2024 Approved THOMAS FINNILA
ELECTRICAL-Rough 12/6/2024 Not Ready for Inspection THOMAS FINNILA
Wood Frame 12/6/2024 Corrections Issued THOMAS FINNILA
Gas Test 12/12/2024 Approved THOMAS FINNILA
Insulation 12/12/2024 Partial Approval THOMAS FINNILA
Wood Frame 12/12/2024 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 12/17/2024 Conditional Approval THOMAS FINNILA
ELECTRICAL-Rough 12/20/2024 Approved THOMAS FINNILA
HVAC-Rough 12/23/2024 Approved THOMAS FINNILA
Wood Frame 12/23/2024 Conditional Approval THOMAS FINNILA
HVAC-Rough 12/24/2024 No Access for Inspection GEVORK IPCHYAN
Interior/Exterior Lathing 12/24/2024 No Access for Inspection GEVORK IPCHYAN
Wood Frame 12/24/2024 No Access for Inspection GEVORK IPCHYAN
Interior/Exterior Lathing 12/26/2024 Partial Approval THOMAS FINNILA
Insulation 1/6/2025 Approved JOHN COLEMAN
Drywall Nailing 1/22/2025 Approved JOHN COLEMAN
Green Building Rough 1/22/2025 Approved JOHN COLEMAN
Shower Pan 1/31/2025 Approved THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 2/25/2025 Not Ready for Inspection JOHN COLEMAN
Interior/Exterior Lathing 2/25/2025 Not Ready for Inspection JOHN COLEMAN
Interior/Exterior Lathing 2/26/2025 Partial Approval SCOTT SOBEL
Special/Order Compliance 2/26/2025 Partial Inspection SCOTT SOBEL
Footing/Foundation/Slab 3/3/2025 Conditional Approval THOMAS FINNILA
Interior/Exterior Lathing 3/3/2025 Approved THOMAS FINNILA
Interior/Exterior Lathing 3/19/2025 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 3/24/2025 Partial Approval JOHN KIDWELL
Service/Power Release 4/9/2025 Not Ready for Inspection THOMAS FINNILA
Shower Pan 4/14/2025 Approved JOHN COLEMAN
Gas Test 4/18/2025 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 4/21/2025 Conditional Approval THOMAS FINNILA
Service/Power Release 4/21/2025 Approved THOMAS FINNILA
Gas Test 4/23/2025 Approved THOMAS FINNILA
HVAC-Final 4/23/2025 Approved THOMAS FINNILA
PLUMBING-Final 4/23/2025 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 5/6/2025 Not Ready for Inspection JOHN COLEMAN
ELECTRICAL-Final 5/7/2025 Approved JUAN ALVARADO
BUILDING-Rough-Frame 5/8/2025 Approved JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 5/8/2025 SGSOV Not Ready JOHN COLEMAN
PLUMBING-Final 5/14/2025 Corrections Issued THOMAS FINNILA
Final 11/21/2025 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 11/21/2025 Approved THOMAS FINNILA
Green Building Final 11/21/2025 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 11/21/2025 SGSOV Approved THOMAS FINNILA
Smoke Detectors 11/21/2025 Approved THOMAS FINNILA
Final 12/18/2025 Corrections Issued THOMAS FINNILA
PLUMBING-Final 12/18/2025 Not Ready for Inspection THOMAS FINNILA
Final 2/4/2026 Corrections Issued MORRIS JACKSON
PLUMBING-Final 2/4/2026 Not Ready for Inspection MORRIS JACKSON
Final 2/24/2026 Partial Inspection THOMAS FINNILA
Final 4/27/2026 OK to Issue CofO THOMAS FINNILA