5877-5879 N FAIRHAVEN AVE 91367

Certificate Information: 5877-5879 N FAIRHAVEN AVE 91367

Application / Permit
24014-20000-01710
Plan Check / Job No.
B24VN05643
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 32'-6" X 17'-7" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e); ADD 42'-1" X 10'-10" IRREGULAR SHAPED ADDITION TO EXISTING SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
Permit Issued
Issued on 8/21/2024
Issuing Office
Valley
Current Status
CofO Issued on 4/29/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/24/2024 APPLICANT
Assigned to Plan Check Engineer 5/9/2024 SELLA BENYAMIN
Corrections Issued 5/16/2024 SELLA BENYAMIN
Quality Review Completed 5/17/2024 STEVEN KIM
Building Plans Picked Up 5/20/2024 APPLICANT
Plan Check Approved 7/12/2024 SELLA BENYAMIN
Issued 8/21/2024 APPLICANT
CofO in Progress 2/19/2026 GEVORK IPCHYAN
Permit Finaled 4/29/2026 JOHN JANSON
CofO Issued 4/29/2026 JOHN JANSON
Permit Finaled 4/29/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/22/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 5/22/2024 BIAINA HARITUNIAN
Grading Pre-Inspection Cleared 6/24/2024 GERMAN RODRIGUEZ MENDOZA
Sewer availability Cleared 6/26/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 7/1/2024 BIAINA HARITUNIAN
GPI Written Notices Cleared 7/2/2024 SELLA BENYAMIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/28/2025 Partial Approval GEVORK IPCHYAN
METHANE-Subgrade 4/29/2025 Partial Approval SCOTT SOBEL
PLUMBING-Rough 4/29/2025 Corrections Issued SCOTT SOBEL
Sewer 4/29/2025 Approved SCOTT SOBEL
Underground Mechanical 4/29/2025 Partial Approval SCOTT SOBEL
METHANE-Barrier 5/7/2025 Approved GEVORK IPCHYAN
METHANE-Rough 5/7/2025 Partial Approval GEVORK IPCHYAN
PLUMBING-Rough 5/7/2025 Partial Approval GEVORK IPCHYAN
Deputy Drilled-In Anchors 5/13/2025 Conditional Approval TROY SANDERS
Deputy Drilled-In Anchors 5/23/2025 Conditional Approval ROBERT GOLD
Deputy Drilled-In Anchors 6/20/2025 Conditional Approval TROY SANDERS
Excavation/Setback/Form/Re-Bar 6/20/2025 Approved GEVORK IPCHYAN
PLUMBING-Rough 7/31/2025 Approved GEVORK IPCHYAN
ELECTRICAL-Rough 8/26/2025 Approved GEVORK IPCHYAN
HVAC-Rough 8/26/2025 Approved GEVORK IPCHYAN
BUILDING-Rough-Frame 9/15/2025 Partial Approval GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 9/15/2025 Partial Approval GEVORK IPCHYAN
Green Building Rough 9/15/2025 Approved GEVORK IPCHYAN
Insulation 9/15/2025 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 9/15/2025 Partial Approval GEVORK IPCHYAN
Drywall Nailing 9/26/2025 Approved ROBERT GOLD
Shower Pan 10/16/2025 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 11/13/2025 Partial Approval GEVORK IPCHYAN
BUILDING-Rough-Frame 12/12/2025 Partial Approval GEVORK IPCHYAN
ELECTRICAL-Final 12/12/2025 Not Ready for Inspection GEVORK IPCHYAN
Final 12/12/2025 Not Ready for Inspection GEVORK IPCHYAN
Footing/Foundation/Slab 12/12/2025 Approved GEVORK IPCHYAN
Green Building Final 12/12/2025 Approved GEVORK IPCHYAN
HVAC-Final 12/12/2025 Approved GEVORK IPCHYAN
METHANE-Final 12/12/2025 Not Ready for Inspection GEVORK IPCHYAN
METHANE-Rough 12/12/2025 Approved GEVORK IPCHYAN
METHANE-Subgrade 12/12/2025 Approved GEVORK IPCHYAN
PLUMBING-Final 12/12/2025 Not Ready for Inspection GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 12/12/2025 SGSOV Not Ready GEVORK IPCHYAN
Smoke Detectors 12/12/2025 Approved GEVORK IPCHYAN
BUILDING-Rough-Frame 2/18/2026 Approved GEVORK IPCHYAN
ELECTRICAL-Final 2/18/2026 Approved GEVORK IPCHYAN
Final 2/18/2026 OK to Issue CofO GEVORK IPCHYAN
HVAC-Final 2/18/2026 Approved GEVORK IPCHYAN
METHANE-Final 2/18/2026 Approved GEVORK IPCHYAN
METHANE-Rough 2/18/2026 Approved GEVORK IPCHYAN
PLUMBING-Final 2/18/2026 Approved GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 2/18/2026 SGSOV Approved GEVORK IPCHYAN
Special/Order Compliance 3/4/2026 Corrections Issued GEVORK IPCHYAN