5877-5879 N FAIRHAVEN AVE 91367
Certificate Information: 5877-5879 N FAIRHAVEN AVE 91367
- Application / Permit
- 24014-20000-01710
- Plan Check / Job No.
- B24VN05643
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 32'-6" X 17'-7" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e); ADD 42'-1" X 10'-10" IRREGULAR SHAPED ADDITION TO EXISTING SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
- Permit Issued
- Issued on 8/21/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/29/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2024 | SELLA BENYAMIN |
| Corrections Issued | 5/16/2024 | SELLA BENYAMIN |
| Quality Review Completed | 5/17/2024 | STEVEN KIM |
| Building Plans Picked Up | 5/20/2024 | APPLICANT |
| Plan Check Approved | 7/12/2024 | SELLA BENYAMIN |
| Issued | 8/21/2024 | APPLICANT |
| CofO in Progress | 2/19/2026 | GEVORK IPCHYAN |
| Permit Finaled | 4/29/2026 | JOHN JANSON |
| CofO Issued | 4/29/2026 | JOHN JANSON |
| Permit Finaled | 4/29/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/22/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 5/22/2024 | BIAINA HARITUNIAN |
| Grading Pre-Inspection | Cleared | 6/24/2024 | GERMAN RODRIGUEZ MENDOZA |
| Sewer availability | Cleared | 6/26/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2024 | BIAINA HARITUNIAN |
| GPI Written Notices | Cleared | 7/2/2024 | SELLA BENYAMIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/28/2025 | Partial Approval | GEVORK IPCHYAN |
| METHANE-Subgrade | 4/29/2025 | Partial Approval | SCOTT SOBEL |
| PLUMBING-Rough | 4/29/2025 | Corrections Issued | SCOTT SOBEL |
| Sewer | 4/29/2025 | Approved | SCOTT SOBEL |
| Underground Mechanical | 4/29/2025 | Partial Approval | SCOTT SOBEL |
| METHANE-Barrier | 5/7/2025 | Approved | GEVORK IPCHYAN |
| METHANE-Rough | 5/7/2025 | Partial Approval | GEVORK IPCHYAN |
| PLUMBING-Rough | 5/7/2025 | Partial Approval | GEVORK IPCHYAN |
| Deputy Drilled-In Anchors | 5/13/2025 | Conditional Approval | TROY SANDERS |
| Deputy Drilled-In Anchors | 5/23/2025 | Conditional Approval | ROBERT GOLD |
| Deputy Drilled-In Anchors | 6/20/2025 | Conditional Approval | TROY SANDERS |
| Excavation/Setback/Form/Re-Bar | 6/20/2025 | Approved | GEVORK IPCHYAN |
| PLUMBING-Rough | 7/31/2025 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Rough | 8/26/2025 | Approved | GEVORK IPCHYAN |
| HVAC-Rough | 8/26/2025 | Approved | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 9/15/2025 | Partial Approval | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2025 | Partial Approval | GEVORK IPCHYAN |
| Green Building Rough | 9/15/2025 | Approved | GEVORK IPCHYAN |
| Insulation | 9/15/2025 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 9/15/2025 | Partial Approval | GEVORK IPCHYAN |
| Drywall Nailing | 9/26/2025 | Approved | ROBERT GOLD |
| Shower Pan | 10/16/2025 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 11/13/2025 | Partial Approval | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 12/12/2025 | Partial Approval | GEVORK IPCHYAN |
| ELECTRICAL-Final | 12/12/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Final | 12/12/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Footing/Foundation/Slab | 12/12/2025 | Approved | GEVORK IPCHYAN |
| Green Building Final | 12/12/2025 | Approved | GEVORK IPCHYAN |
| HVAC-Final | 12/12/2025 | Approved | GEVORK IPCHYAN |
| METHANE-Final | 12/12/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| METHANE-Rough | 12/12/2025 | Approved | GEVORK IPCHYAN |
| METHANE-Subgrade | 12/12/2025 | Approved | GEVORK IPCHYAN |
| PLUMBING-Final | 12/12/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 12/12/2025 | SGSOV Not Ready | GEVORK IPCHYAN |
| Smoke Detectors | 12/12/2025 | Approved | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 2/18/2026 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Final | 2/18/2026 | Approved | GEVORK IPCHYAN |
| Final | 2/18/2026 | OK to Issue CofO | GEVORK IPCHYAN |
| HVAC-Final | 2/18/2026 | Approved | GEVORK IPCHYAN |
| METHANE-Final | 2/18/2026 | Approved | GEVORK IPCHYAN |
| METHANE-Rough | 2/18/2026 | Approved | GEVORK IPCHYAN |
| PLUMBING-Final | 2/18/2026 | Approved | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 2/18/2026 | SGSOV Approved | GEVORK IPCHYAN |
| Special/Order Compliance | 3/4/2026 | Corrections Issued | GEVORK IPCHYAN |