11012 N WESCOTT AVE 91040
Certificate Information: 11012 N WESCOTT AVE 91040
- Application / Permit
- 24014-20000-01707
- Plan Check / Job No.
- B24VN05615
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan: New 10'-6" x 6'-9" Attached Lauundry Room to (E) 1-Story SFD w/Attached Garage
- Permit Issued
- Issued on 6/6/2024
- Issuing Office
- Current Status
- CofO Issued on 12/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/26/2024 | DAVID CASTILLO |
| Corrections Issued | 4/30/2024 | DAVID CASTILLO |
| Plan Check Approved | 6/5/2024 | DAVID CASTILLO |
| Issued | 6/6/2024 | APPLICANT |
| CofO in Progress | 11/22/2024 | WILLIAM WREN |
| Permit Finaled | 12/17/2024 | RUBEN SALAS |
| CofO Issued | 12/17/2024 | RUBEN SALAS |
| Permit Finaled | 12/17/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/4/2024 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/7/2024 | JOHN LIN |
| Grading Pre-Inspection | Cleared | 5/31/2024 | VASIL MIHALEV |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/10/2024 | Partial Inspection | WILLIAM WREN |
| Footing/Foundation/Slab | 6/21/2024 | Partial Inspection | WILLIAM WREN |
| Pre-Inspection | 6/21/2024 | Partial Inspection | WILLIAM WREN |
| Deputy Drilled-In Anchors | 10/24/2024 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 10/28/2024 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 10/28/2024 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2024 | Approved | WILLIAM WREN |
| Footing/Foundation/Slab | 10/28/2024 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 10/28/2024 | Approved | WILLIAM WREN |
| Sewer | 10/28/2024 | Approved | WILLIAM WREN |
| Insulation | 10/30/2024 | Approved | WILLIAM WREN |
| Drywall Nailing | 11/1/2024 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 11/1/2024 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 11/19/2024 | Approved | WILLIAM WREN |
| Final | 11/19/2024 | OK to Issue CofO | WILLIAM WREN |
| Green Building Final | 11/19/2024 | Approved | WILLIAM WREN |
| Green Building Rough | 11/19/2024 | Approved | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 11/19/2024 | SGSOV Approved | WILLIAM WREN |
| Smoke Detectors | 11/19/2024 | Approved | WILLIAM WREN |