7955 N PONCE AVE 91304

Certificate Information: 7955 N PONCE AVE 91304

Application / Permit
24014-20000-01706
Plan Check / Job No.
B24VN05609
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) IRREG SHAPED ADDITION TO (E) SFD AND ATT GARAGE
Permit Issued
Issued on 5/9/2024
Issuing Office
Current Status
CofO Issued on 8/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/24/2024 APPLICANT
Assigned to Plan Check Engineer 5/2/2024 JEROME MAGAT PALMA
Corrections Issued 5/4/2024 JEROME MAGAT PALMA
Building Plans Picked Up 5/6/2024 APPLICANT
Plan Check Approved 5/9/2024 ISIS ARGUETA
Issued 5/9/2024 APPLICANT
CofO in Progress 8/9/2024 JEFFREY HARTLINE
CofO Issued 8/14/2024 JOHN JANSON
Permit Finaled 8/14/2024 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/6/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 5/6/2024 CARLOS AGUILERA
Sewer availability Cleared 5/6/2024 CARLOS AGUILERA

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Preferred Home Builders Inc; Lic. No.: 773147-B 21204 VANOWEN STREET      CANOGA PARK, CA 91303

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/28/2024 Partial Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 5/30/2024 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 5/30/2024 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 6/3/2024 Conditional Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 6/14/2024 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 6/20/2024 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 6/20/2024 Approved CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 6/21/2024 Conditional Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 6/25/2024 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 6/25/2024 Not Ready for Inspection CHRIS CHRISTENSEN
Rough-Elec/Plmb/HVAC 6/25/2024 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 7/1/2024 Approved CHRIS CHRISTENSEN
Green Building Rough 7/1/2024 Approved CHRIS CHRISTENSEN
HVAC-Rough 7/1/2024 Approved CHRIS CHRISTENSEN
Insulation 7/1/2024 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 7/1/2024 Partial Approval CHRIS CHRISTENSEN
Shower Pan 7/1/2024 Approved CHRIS CHRISTENSEN
Drywall Nailing 7/3/2024 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 7/3/2024 Partial Approval CHRIS CHRISTENSEN
Drywall Nailing 7/5/2024 No Access for Inspection JEFFREY HARTLINE
Final 8/6/2024 Corrections Issued JEFFREY HARTLINE
Footing/Foundation/Slab 8/6/2024 Approved JEFFREY HARTLINE
Green Building Final 8/6/2024 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 8/6/2024 SGSOV Not Ready JEFFREY HARTLINE
Smoke Detectors 8/6/2024 Approved JEFFREY HARTLINE
ELECTRICAL-Final 8/8/2024 Approved JEFFREY HARTLINE
Final 8/8/2024 OK to Issue CofO JEFFREY HARTLINE
HVAC-Final 8/8/2024 Approved JEFFREY HARTLINE
PLUMBING-Final 8/8/2024 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 8/8/2024 SGSOV Approved JEFFREY HARTLINE