5018-5020 N MAMMOTH AVE 91423
Certificate Information: 5018-5020 N MAMMOTH AVE 91423
- Application / Permit
- 24014-20000-01704
- Plan Check / Job No.
- B24VN05600
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED IRREG SHAPED 22'4"X32'3" ACCESSORY DWELLING UNIT ADDITION TO (E)1-STORY SFD W/ ATT GARAGE PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 10/10/2024
- Issuing Office
- Current Status
- Issued on 10/10/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/2/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 5/3/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 5/22/2024 | APPLICANT |
| Issued | 10/10/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/4/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 6/4/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 8/21/2024 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 10/7/2024 | RIDWAN HARDY |
Contact Information
| Architect | Lee,, Kenneth David; Lic. No.: C10141 | 16501 ACADEMIA DRIVE ENCINO, CA 91436 |
| Contractor | Flip It Homes Inc; Lic. No.: 1043456-B | 20501 VENTURA BLVD #135 WOODLAND HILLS, CA 91364 |
| Engineer | Shakiban,, George; Lic. No.: C39908 | 23945 CALABASAS RD STE 101 CALABASAS, CA 91302 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/7/2024 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 11/8/2024 | Corrections Issued | MISAEL ESPARZA |
| Sewer | 11/8/2024 | Approved | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 11/13/2024 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 11/22/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Wood Frame | 11/22/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 11/26/2024 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 11/26/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 11/26/2024 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2024 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 12/2/2024 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2024 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2024 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 1/23/2025 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 1/23/2025 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 1/23/2025 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 1/24/2025 | Partial Approval | JACK KARGODORIAN |
| Green Building Rough | 1/24/2025 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/5/2025 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/7/2025 | Approved | MISAEL ESPARZA |
| Deputy Wood Construction | 2/7/2025 | Conditional Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2025 | Approved | MISAEL ESPARZA |
| Insulation | 2/7/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 2/7/2025 | Partial Approval | MISAEL ESPARZA |
| Insulation | 2/13/2025 | Partial Approval | MISAEL ESPARZA |
| Drywall Nailing | 2/20/2025 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 2/20/2025 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 4/14/2025 | Corrections Issued | MISAEL ESPARZA |
| Final | 4/14/2025 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 4/14/2025 | Approved | MISAEL ESPARZA |
| Green Building Final | 4/14/2025 | Approved | MISAEL ESPARZA |
| HVAC-Final | 4/14/2025 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 4/14/2025 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 4/14/2025 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 4/14/2025 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 5/22/2025 | Corrections Issued | MISAEL ESPARZA |
| Final | 5/22/2025 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Final | 5/22/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Final | 5/22/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 5/22/2025 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 5/22/2025 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 5/23/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 5/23/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 5/23/2025 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 5/23/2025 | Approved | MISAEL ESPARZA |