14012-14014 W CANTLAY ST 91405

Certificate Information: 14012-14014 W CANTLAY ST 91405

Application / Permit
24014-20000-01683
Plan Check / Job No.
B24VN05534
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: CONVERT EXISTING GARAGE WITH 2-STORY ADDITION INTO A 2-STORY (24'-8 1/4" X 19'-1 1/4") ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (e)
Permit Issued
Issued on 7/8/2025
Issuing Office
Current Status
Issued on 7/8/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/24/2024 APPLICANT
Assigned to Plan Check Engineer 5/9/2024 VAHAN JIVALAGIAN
Corrections Issued 5/15/2024 VAHAN JIVALAGIAN
Quality Review Completed 5/17/2024 OMID HEDAYAT
Applicant returned to address corrections 10/21/2024 VAHAN JIVALAGIAN
Plan Check Approved 11/26/2024 VAHAN JIVALAGIAN
Issued 7/8/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/20/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 5/20/2024 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 5/20/2024 LEE GUILBEAUX
Sewer availability Cleared 5/20/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 5/20/2024 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/4/2025 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 8/7/2025 Partial Approval JENNIFER RABUCHIN
Deputy Drilled-In Anchors 8/18/2025 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 8/18/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Rough 8/18/2025 Partial Approval NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 8/27/2025 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 12/3/2025 Corrections Issued DAVID MATSON
Interior/Exterior Lathing 12/3/2025 Not Ready for Inspection DAVID MATSON
PLUMBING-Rough 12/3/2025 Approved DAVID MATSON
ELECTRICAL-Rough 12/4/2025 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 12/4/2025 Approved OGANES TARAKHCHYAN
HVAC-Rough 12/4/2025 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 12/8/2025 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 12/8/2025 Approved JAVIER RAMOS JR
Wood Frame 12/12/2025 Approved WAYNE REGESTER
Insulation 12/19/2025 Approved OGANES TARAKHCHYAN
Drywall Nailing 1/13/2026 Approved OGANES TARAKHCHYAN
Green Building Rough 1/13/2026 Approved OGANES TARAKHCHYAN
Shower Pan 1/14/2026 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 2/17/2026 Partial Approval OGANES TARAKHCHYAN
Interior/Exterior Lathing 3/9/2026 Approved OGANES TARAKHCHYAN