14012-14014 W CANTLAY ST 91405
Certificate Information: 14012-14014 W CANTLAY ST 91405
- Application / Permit
- 24014-20000-01683
- Plan Check / Job No.
- B24VN05534
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: CONVERT EXISTING GARAGE WITH 2-STORY ADDITION INTO A 2-STORY (24'-8 1/4" X 19'-1 1/4") ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (e)
- Permit Issued
- Issued on 7/8/2025
- Issuing Office
- Current Status
- Issued on 7/8/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2024 | VAHAN JIVALAGIAN |
| Corrections Issued | 5/15/2024 | VAHAN JIVALAGIAN |
| Quality Review Completed | 5/17/2024 | OMID HEDAYAT |
| Applicant returned to address corrections | 10/21/2024 | VAHAN JIVALAGIAN |
| Plan Check Approved | 11/26/2024 | VAHAN JIVALAGIAN |
| Issued | 7/8/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/20/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2024 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 5/20/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 5/20/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 5/20/2024 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/4/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 8/7/2025 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 8/18/2025 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 8/18/2025 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 8/18/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2025 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2025 | Corrections Issued | DAVID MATSON |
| Interior/Exterior Lathing | 12/3/2025 | Not Ready for Inspection | DAVID MATSON |
| PLUMBING-Rough | 12/3/2025 | Approved | DAVID MATSON |
| ELECTRICAL-Rough | 12/4/2025 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2025 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 12/4/2025 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 12/8/2025 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 12/8/2025 | Approved | JAVIER RAMOS JR |
| Wood Frame | 12/12/2025 | Approved | WAYNE REGESTER |
| Insulation | 12/19/2025 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 1/13/2026 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 1/13/2026 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 1/14/2026 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 2/17/2026 | Partial Approval | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 3/9/2026 | Approved | OGANES TARAKHCHYAN |