14825 W GREENLEAF ST 91403
Certificate Information: 14825 W GREENLEAF ST 91403
- Application / Permit
- 24014-20000-01678
- Plan Check / Job No.
- B24VN05506
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 1232 SQFT 2ND STORY ADDITION AND 18 SQFT 1ST FLOOR ADDITION TO EXISTING 1-STORY SINGLE FAMILY DWELLING W/NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 6/27/2024
- Issuing Office
- Current Status
- CofO in Progress on 6/1/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2024 | PETER MOSESIAN |
| Corrections Issued | 4/28/2024 | PETER MOSESIAN |
| Quality Review Completed | 4/30/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 5/1/2024 | APPLICANT |
| Plan Check Approved | 6/6/2024 | PETER MOSESIAN |
| Issued | 6/27/2024 | APPLICANT |
| CofO in Progress | 6/1/2026 | MISAEL ESPARZA |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/4/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/6/2024 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 6/6/2024 | PETER MOSESIAN |
Contact Information
| Contractor | Delaware Pacific Builders Inc; Lic. No.: 1121593-B | 1123 NORTH ALLEN AVE PASADENA, CA 91104 |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/10/2024 | Approved | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 8/29/2024 | Conditional Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 9/4/2024 | Approved | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/4/2024 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/5/2024 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2024 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2024 | Partial Approval | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 9/30/2024 | Conditional Approval | JUAN VALENZUELA |
| Deputy Wood Construction | 10/24/2024 | Conditional Approval | ROBERT GOLD |
| Wood Frame | 11/5/2024 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2024 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2024 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 12/2/2024 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 12/6/2024 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 12/6/2024 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 12/13/2024 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 12/13/2024 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 12/13/2024 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 1/2/2025 | Partial Approval | MISAEL ESPARZA |
| Deputy Wood Construction | 1/15/2025 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 1/28/2025 | Approved | MISAEL ESPARZA |
| Green Building Rough | 1/28/2025 | Approved | MISAEL ESPARZA |
| Insulation | 1/28/2025 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 2/4/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 2/4/2025 | Approved | MICHAEL CORTEZ |
| Shower Pan | 2/4/2025 | Approved | MICHAEL CORTEZ |
| Special/Order Compliance | 2/25/2025 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 6/11/2025 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Final | 6/11/2025 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 6/11/2025 | Corrections Issued | MISAEL ESPARZA |
| Final | 6/12/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 6/12/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 6/12/2025 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 6/12/2025 | Approved | MISAEL ESPARZA |
| Final | 11/19/2025 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 11/19/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 5/28/2026 | OK to Issue CofO | MISAEL ESPARZA |
| Green Building Final | 5/28/2026 | Approved | MISAEL ESPARZA |