6415 N CAMELLIA AVE 91606
Certificate Information: 6415 N CAMELLIA AVE 91606
- Application / Permit
- 24014-20000-01668
- Plan Check / Job No.
- B24VN05477
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 5'-5" x 5'-3" ADDITION OF WALK IN CLOSET AND NEW 15'-1" X 16'-9" STORAGE UNIT TO THE EXISTING ACCESSORY DWELLING UNIT. ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 4/26/2024
- Issuing Office
- Current Status
- CofO Issued on 11/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2024 | ARAMIK SHAHMIRZAIAN |
| Corrections Issued | 4/22/2024 | ARAMIK SHAHMIRZAIAN |
| Issued | 4/26/2024 | APPLICANT |
| CofO in Progress | 9/12/2024 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 11/7/2024 | DANIEL ORRANTE |
| CofO Issued | 11/7/2024 | DANIEL ORRANTE |
| Permit Finaled | 11/7/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2024 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 4/22/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 4/22/2024 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 4/26/2024 | WALTER RAMIREZ |
| Construction within easement | Cleared | 4/26/2024 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/6/2024 | Partial Inspection | JOHN COLEMAN |
| Deputy Drilled-In Anchors | 5/21/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 5/21/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 6/10/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 6/18/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 6/18/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 6/18/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 6/18/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 7/11/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 7/11/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 8/5/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 8/9/2024 | Approved | MICHAEL CORTEZ |
| Final | 8/26/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Smoke Detectors | 8/26/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 8/29/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 8/29/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 9/12/2024 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |