6415 N CAMELLIA AVE 91606

Certificate Information: 6415 N CAMELLIA AVE 91606

Application / Permit
24014-20000-01668
Plan Check / Job No.
B24VN05477
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 5'-5" x 5'-3" ADDITION OF WALK IN CLOSET AND NEW 15'-1" X 16'-9" STORAGE UNIT TO THE EXISTING ACCESSORY DWELLING UNIT. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 4/26/2024
Issuing Office
Current Status
CofO Issued on 11/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2024 APPLICANT
Assigned to Plan Check Engineer 4/22/2024 ARAMIK SHAHMIRZAIAN
Corrections Issued 4/22/2024 ARAMIK SHAHMIRZAIAN
Issued 4/26/2024 APPLICANT
CofO in Progress 9/12/2024 ROBERTO PALACIOS-LOPEZ
Permit Finaled 11/7/2024 DANIEL ORRANTE
CofO Issued 11/7/2024 DANIEL ORRANTE
Permit Finaled 11/7/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/22/2024 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 4/22/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 4/22/2024 LEE GUILBEAUX
Construction near power lines Cleared 4/26/2024 WALTER RAMIREZ
Construction within easement Cleared 4/26/2024 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/6/2024 Partial Inspection JOHN COLEMAN
Deputy Drilled-In Anchors 5/21/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 5/21/2024 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 5/31/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 6/10/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 6/18/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 6/18/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 6/18/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 6/18/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 7/11/2024 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 7/11/2024 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 7/11/2024 Approved ROBERTO PALACIOS-LOPEZ
Insulation 8/5/2024 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 8/9/2024 Approved MICHAEL CORTEZ
Final 8/26/2024 Corrections Issued CHRISTOPHER ROJAS
Smoke Detectors 8/26/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Final 8/29/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 8/29/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 9/12/2024 OK to Issue CofO ROBERTO PALACIOS-LOPEZ