11202 W SYLVAN ST 91606

Certificate Information: 11202 W SYLVAN ST 91606

Application / Permit
24014-20000-01623
Plan Check / Job No.
B24VN05326
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*EPLAN* ADD 7'-1" X 32'-4" IRREGULAR SHAPED ADDITION TO FIRST FLOOR; ADD 11'-6" X 22' 1-CAR GARAGE; 21'-11" X 27'-2" SECOND FLOOR ADDITION
Permit Issued
Issued on 8/28/2024
Issuing Office
Current Status
CofO Issued on 1/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/19/2024 APPLICANT
Assigned to Plan Check Engineer 5/2/2024 SELLA BENYAMIN
Corrections Issued 5/9/2024 SELLA BENYAMIN
Quality Review Completed 5/13/2024 STEVEN KIM
Plan Check Approved 8/28/2024 SELLA BENYAMIN
Issued 8/28/2024 APPLICANT
CofO in Progress 1/20/2026 MATTHEW NELSON
Permit Finaled 1/28/2026 RUBEN SALAS
CofO Issued 1/28/2026 RUBEN SALAS
Permit Finaled 1/28/2026 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/9/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 7/9/2024 BIAINA HARITUNIAN
Sewer availability Cleared 7/9/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Casillas,, Rafael Ortega; Lic. No.: C68234 1937 S BRADSHAWE AVE      MONTEREY PARK, CA 91754
Engineer Casillas,, Rafael Ortega; Lic. No.: NA68234       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/27/2025 Partial Inspection MISAEL ESPARZA
Underground Mechanical 1/27/2025 Partial Inspection MISAEL ESPARZA
Deputy Drilled-In Anchors 2/3/2025 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 2/11/2025 Corrections Issued JOSE AVILA
Deputy Drilled-In Anchors 2/18/2025 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 2/18/2025 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 2/27/2025 Corrections Issued JOSE AVILA
Deputy Drilled-In Anchors 3/10/2025 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 3/17/2025 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 4/11/2025 Corrections Issued JOSE AVILA
Deputy Wood Construction 4/15/2025 Conditional Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 4/15/2025 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 5/8/2025 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 5/27/2025 Corrections Issued JOSE AVILA
HVAC-Rough 5/27/2025 Corrections Issued JOSE AVILA
PLUMBING-Rough 5/27/2025 Approved JOSE AVILA
ELECTRICAL-Rough 6/9/2025 No Access for Inspection JOSE AVILA
HVAC-Rough 6/9/2025 No Access for Inspection JOSE AVILA
PLUMBING-Rough 6/9/2025 No Access for Inspection JOSE AVILA
ELECTRICAL-Rough 6/13/2025 Conditional Approval JOSE AVILA
HVAC-Rough 6/13/2025 Conditional Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 6/25/2025 Partial Approval JOSE AVILA
Shower Pan 6/27/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 6/30/2025 Approved JOSE AVILA
BUILDING-Rough-Frame 7/11/2025 Approved JOSE AVILA
Insulation 7/11/2025 Approved JOSE AVILA
Drywall Nailing 7/16/2025 Approved LOUIS ESCOTO
Underground Mechanical 9/30/2025 Not Ready for Inspection MICHAEL CORTEZ
Underground Mechanical 10/8/2025 Approved JOSE AVILA
Gas Test 11/17/2025 Approved JOSE AVILA
Final 1/16/2026 OK to Issue CofO MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 1/16/2026 SGSOV Approved MATTHEW NELSON
Smoke Detectors 1/16/2026 Approved MATTHEW NELSON