6616-6618 N BEN AVE 91606

Certificate Information: 6616-6618 N BEN AVE 91606

Application / Permit
24014-20000-01616
Plan Check / Job No.
B24VN05315
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Conversion of existing attached garage with (17'-11" x 8') first story addition and addition of (29'-3" x 24' Irregular Shape) second story into an Accessory Dwelling Unit per LAMC 12.22 A.33 (c) and (e)
Permit Issued
Issued on 6/13/2024
Issuing Office
Valley
Current Status
CofO Issued on 2/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/18/2024 APPLICANT
Assigned to Plan Check Engineer 4/25/2024 VAHAN JIVALAGIAN
Corrections Issued 4/28/2024 VAHAN JIVALAGIAN
Quality Review Completed 4/30/2024 OMID HEDAYAT
Building Plans Picked Up 5/1/2024 APPLICANT
Plan Check Approved 6/13/2024 VAHAN JIVALAGIAN
Issued 6/13/2024 APPLICANT
CofO in Progress 12/27/2024 JOSE AVILA
Permit Finaled 2/4/2025 RUBEN SALAS
CofO Issued 2/4/2025 RUBEN SALAS
Permit Finaled 2/4/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/11/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 6/11/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 6/12/2024 BIAINA HARITUNIAN
Sewer availability Cleared 6/12/2024 BIAINA HARITUNIAN

Contact Information

Contractor J R D Construction & Development Inc; Lic. No.: 1011498-B 6159 MELVIN AVE      TARZANA, CA 91356
Engineer Basma,, Ali J; Lic. No.: C53080 6047 TAMPA AVE   SUITE 304    TARZANA, CA 91356

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/26/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 7/2/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 7/5/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Deputy Drilled-In Anchors 7/9/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 7/12/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Deputy Wood Construction 8/9/2024 Conditional Approval DAVID MATSON
ELECTRICAL-Rough 8/12/2024 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 8/12/2024 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 8/12/2024 Not Ready for Inspection JENNIFER RABUCHIN
Wood Frame 8/12/2024 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 8/15/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 8/15/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Rough-Elec/Plmb/HVAC 8/20/2024 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 8/23/2024 Approved ROBERTO PALACIOS-LOPEZ
Insulation 8/23/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 8/28/2024 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 8/28/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 8/28/2024 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 9/10/2024 Approved ROBERTO PALACIOS-LOPEZ
Insulation 9/10/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 11/22/2024 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 11/22/2024 Approved MATTHEW NELSON
Green Building Final 11/22/2024 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 11/22/2024 SGSOV Approved MATTHEW NELSON
Smoke Detectors 11/22/2024 Approved MATTHEW NELSON
Final 12/20/2024 Not Ready for Inspection JOSE AVILA
Green Building Final 12/20/2024 Approved JOSE AVILA
Final 12/24/2024 OK to Issue CofO JOSE AVILA
Service/Power Release 1/8/2025 Approved JOSE AVILA