5903 N DONNA AVE 91356
Certificate Information: 5903 N DONNA AVE 91356
- Application / Permit
- 24014-20000-01604
- Plan Check / Job No.
- B24VN05282
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: REMODEL, CONVERT A PORTION OF (E) GARAGE TO BE PART OF S.F.D., AND ADDITION TO (E) S.F.D. PER ENGINEERING
- Permit Issued
- Issued on 6/3/2024
- Issuing Office
- Current Status
- CofO in Progress on 3/6/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2024 | ALFRED RAMIREZ |
| Corrections Issued | 4/23/2024 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 5/13/2024 | PINANK PATEL |
| Applicant returned to address corrections | 5/24/2024 | PINANK PATEL |
| Applicant returned to address corrections | 5/29/2024 | SELLA BENYAMIN |
| Plan Check Approved | 5/31/2024 | PINANK PATEL |
| Issued | 6/3/2024 | APPLICANT |
| CofO in Progress | 2/28/2025 | JON MCHUGH |
| No Progress | 3/6/2025 | JON MCHUGH |
| CofO in Progress | 3/6/2025 | JON MCHUGH |
| CofO in Progress | 3/6/2025 | JON MCHUGH |
| CofO in Progress | 4/17/2025 | JON MCHUGH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/30/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 4/30/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 4/30/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mixter,, Thomas J; Lic. No.: C51041 | 2345 COUNTY RD 630 DEL RIO, TX 78840 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/25/2024 | Approved | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 7/26/2024 | Approved | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 7/26/2024 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2024 | Partial Approval | JON MCHUGH |
| Underground Mechanical | 8/1/2024 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2024 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2024 | Partial Approval | JOHN HAYES |
| PLUMBING-Rough | 8/22/2024 | Approved | SCOTT SOBEL |
| ELECTRICAL-Rough | 8/27/2024 | Approved | MORRIS JACKSON |
| HVAC-Rough | 8/27/2024 | Approved | MORRIS JACKSON |
| Shower Pan | 8/27/2024 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 9/6/2024 | Corrections Issued | JON MCHUGH |
| BUILDING-Rough-Frame | 9/13/2024 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 9/13/2024 | Corrections Issued | JON MCHUGH |
| BUILDING-Rough-Frame | 9/18/2024 | Approved | JON MCHUGH |
| ELECTRICAL-Rough | 9/18/2024 | Partial Approval | JON MCHUGH |
| Interior/Exterior Lathing | 9/18/2024 | Partial Approval | JON MCHUGH |
| ELECTRICAL-Rough | 9/23/2024 | Approved | JON MCHUGH |
| Insulation | 9/23/2024 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 9/23/2024 | Approved | JON MCHUGH |
| Drywall Nailing | 10/2/2024 | Approved | TROY SANDERS |
| Final | 1/17/2025 | Corrections Issued | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 1/17/2025 | SGSOV Approved | JON MCHUGH |
| Smoke Detectors | 1/17/2025 | Approved | JON MCHUGH |
| Final | 1/24/2025 | Not Ready for Inspection | JON MCHUGH |
| Final | 2/28/2025 | Not Ready for Inspection | JON MCHUGH |
| Deputy Wood Construction | 3/6/2025 | Partial Approval | SEAN WIRCH |
| Special/Order Compliance | 3/6/2025 | Corrections Issued | JON MCHUGH |
| Final | 4/8/2025 | Corrections Issued | JON MCHUGH |
| Final | 4/17/2025 | OK to Issue CofO | JON MCHUGH |