2746 S WESTGATE AVE 90064

Certificate Information: 2746 S WESTGATE AVE 90064

Application / Permit
24014-20000-01603
Plan Check / Job No.
B24VN05275
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING 1-STORY DETACHED STORAGE (252 SQFT) INTO AN ACCESSORY DWELLING UNIT W/ 1ST AND 2ND STORY ADDITION (552 SQFT) PER LAMC 12.22 A.33(c)(d)
Permit Issued
Issued on 8/6/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/18/2024 APPLICANT
Assigned to Plan Check Engineer 5/2/2024 PETER MOSESIAN
Corrections Issued 5/3/2024 PETER MOSESIAN
Quality Review Completed 5/9/2024 OMID HEDAYAT
Building Plans Picked Up 5/13/2024 APPLICANT
Applicant returned to address corrections 6/6/2024 PETER MOSESIAN
Plan Check Approved 7/22/2024 PETER MOSESIAN
Issued 8/6/2024 APPLICANT
CofO in Progress 1/19/2026 KIRK SANDERS
Permit Finaled 1/21/2026 RICHARD STEINBACH
CofO Issued 1/21/2026 RICHARD STEINBACH
Permit Finaled 1/21/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 5/16/2024 DIANA RENTERIA
Eng Process Fee Ord 176,300 Cleared 5/22/2024 DIANA RENTERIA
Roof/Waste drainage to street Cleared 5/22/2024 DIANA RENTERIA
Sewer availability Cleared 5/22/2024 DIANA RENTERIA
Construction near power lines Cleared 5/30/2024 OSCAR CASTRO
Specific Plan Cleared 7/12/2024 PEDRO AYALA

Contact Information

Contractor Owner-Builder       ,
Engineer Santos,, Michael; Lic. No.: C77657 16202 ORION AVE      CHINO, CA 91708

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/20/2024 Partial Inspection KIRK SANDERS
Footing/Foundation/Slab 10/15/2024 Not Ready for Inspection DANIEL VERA
Sewer 10/15/2024 Approved DANIEL VERA
Underground Mechanical 10/15/2024 Approved DANIEL VERA
Deputy Drilled-In Anchors 10/17/2024 Conditional Approval DANIEL VERA
Footing/Foundation/Slab 10/18/2024 Corrections Issued DANIEL VERA
PLUMBING-Rough 11/22/2024 Approved DANIEL VERA
Deputy Wood Construction 12/9/2024 Conditional Approval DANIEL VERA
ELECTRICAL-Rough 12/10/2024 Not Ready for Inspection DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 12/10/2024 Corrections Issued DANIEL VERA
Green Building Rough 12/10/2024 Not Ready for Inspection DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 12/13/2024 Approved DANIEL VERA
BUILDING-Rough-Frame 1/8/2025 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Rough 1/8/2025 Approved EVAN COOPER
Green Building Rough 1/8/2025 Approved EVAN COOPER
HVAC-Rough 1/8/2025 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 1/10/2025 Approved DANIEL VERA
HVAC-Rough 1/10/2025 Approved DANIEL VERA
Insulation 1/16/2025 Approved DANIEL VERA
Drywall Nailing 1/22/2025 Approved JAYLIN GRAVITTE
Interior/Exterior Lathing 2/13/2025 Approved DANIEL VERA
Shower Pan 2/13/2025 Approved DANIEL VERA
Pre-Inspection 4/28/2025 Approved WILBER ROSALES
ELECTRICAL-Final 1/9/2026 Corrections Issued KIRK SANDERS
HVAC-Final 1/9/2026 Approved KIRK SANDERS
PLUMBING-Final 1/9/2026 Corrections Issued KIRK SANDERS
ELECTRICAL-Final 1/16/2026 Approved KIRK SANDERS
Final 1/16/2026 OK to Issue CofO KIRK SANDERS
Footing/Foundation/Slab 1/16/2026 Approved KIRK SANDERS
Green Building Final 1/16/2026 Approved KIRK SANDERS
PLUMBING-Final 1/16/2026 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 1/16/2026 SGSOV Approved KIRK SANDERS
Service/Power Release 1/16/2026 Approved KIRK SANDERS
Smoke Detectors 1/16/2026 Approved KIRK SANDERS