12652 N HERRICK AVE 91342
Certificate Information: 12652 N HERRICK AVE 91342
- Application / Permit
- 24014-20000-01600
- Plan Check / Job No.
- B24VN05271
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW ADDITIONS TO REAR AND FRONT OF EXISTING SINGLE-FAMILY DWELLING AND NEW ATTACHED PATIO COVER ADDITION AT REAR, ALL WORK PER ENG.
- Permit Issued
- Issued on 10/9/2024
- Issuing Office
- Current Status
- CofO Issued on 12/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2024 | ALEC MOUSAKHANIAN |
| Corrections Issued | 5/24/2024 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 6/17/2024 | ALEC MOUSAKHANIAN |
| No Progress | 7/31/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 9/23/2024 | LUISANGEL VALENZUELA |
| Issued | 10/9/2024 | APPLICANT |
| CofO in Progress | 12/15/2025 | KEVIN BERBERYAN |
| Permit Finaled | 12/31/2025 | RUBEN SALAS |
| CofO Issued | 12/31/2025 | RUBEN SALAS |
| Permit Finaled | 12/31/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/7/2024 | TAL SHEMEN |
| Roof/Waste drainage to street | Cleared | 6/7/2024 | TAL SHEMEN |
| Sewer availability | Cleared | 6/7/2024 | TAL SHEMEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/17/2025 | Corrections Issued | KEVIN BERBERYAN |
| Special/Order Compliance | 1/22/2025 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 4/8/2025 | Partial Approval | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 4/8/2025 | Partial Inspection | KEVIN BERBERYAN |
| PLUMBING-Rough | 4/8/2025 | Partial Approval | KEVIN BERBERYAN |
| Wood Frame | 4/8/2025 | Partial Inspection | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 5/1/2025 | Not Ready for Inspection | WILLIAM WREN |
| Footing/Foundation/Slab | 5/1/2025 | Not Ready for Inspection | WILLIAM WREN |
| Excavation/Setback/Form/Re-Bar | 5/5/2025 | Partial Approval | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 5/12/2025 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 5/15/2025 | Partial Approval | KEVIN BERBERYAN |
| HVAC-Rough | 5/15/2025 | Partial Approval | KEVIN BERBERYAN |
| Insulation | 5/15/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| PLUMBING-Rough | 5/15/2025 | Partial Inspection | KEVIN BERBERYAN |
| Wood Frame | 5/15/2025 | Partial Approval | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 5/20/2025 | Approved | KEVIN BERBERYAN |
| Insulation | 5/20/2025 | Approved | KEVIN BERBERYAN |
| Deputy Wood Construction | 7/10/2025 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 7/15/2025 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 7/15/2025 | Partial Approval | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 7/15/2025 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 7/15/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| HVAC-Rough | 7/15/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| PLUMBING-Rough | 7/15/2025 | Approved | KEVIN BERBERYAN |
| Shower Pan | 8/11/2025 | No Access for Inspection | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 8/13/2025 | Corrections Issued | KEVIN BERBERYAN |
| Shower Pan | 8/13/2025 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 8/18/2025 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 8/18/2025 | Approved | KEVIN BERBERYAN |
| Insulation | 8/18/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 8/18/2025 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 8/26/2025 | Approved | KEVIN BERBERYAN |
| Final | 11/25/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 11/25/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 11/25/2025 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 11/25/2025 | Approved | KEVIN BERBERYAN |
| Final | 12/3/2025 | OK to Issue CofO | KEVIN BERBERYAN |
| Green Building Final | 12/3/2025 | Approved | KEVIN BERBERYAN |