10559 N HELENDALE AVE 91042

Certificate Information: 10559 N HELENDALE AVE 91042

Application / Permit
24014-20000-01595
Plan Check / Job No.
B24VN05229
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: ADDITION TO AND CONVERSION OF (E) DETACHED TWO CAR GARAGE INTO ACCESSORY DWELLING UNIT PER ORDINANCE
Permit Issued
Issued on 5/25/2024
Issuing Office
Current Status
CofO Issued on 6/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/17/2024 APPLICANT
Assigned to Plan Check Engineer 4/22/2024 MINA HABILI
Corrections Issued 4/23/2024 MINA HABILI
Plan Check Approved 5/9/2024 JOSEPH RAFOLS
Issued 5/25/2024 APPLICANT
CofO in Progress 5/28/2025 WILLIAM WREN
Permit Finaled 6/9/2025 RUBEN SALAS
CofO Issued 6/9/2025 RUBEN SALAS
Permit Finaled 6/9/2025 RUBEN SALAS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/26/2024 CHARLES POWELL
Address approval Cleared 4/30/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 4/30/2024 BIAINA HARITUNIAN
Sewer availability Cleared 4/30/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 5/7/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Karapetian,, Arbi; Lic. No.: C79953 6854 FOOTHILL BLVD      TUJUNGA, CA 91042

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/18/2024 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 12/2/2024 Approved WILLIAM WREN
PLUMBING-Rough 12/2/2024 Partial Approval WILLIAM WREN
ELECTRICAL-Rough 1/17/2025 Approved WILLIAM WREN
PLUMBING-Rough 1/17/2025 Approved WILLIAM WREN
Pre-Inspection 1/17/2025 Not Ready for Inspection WILLIAM WREN
BUILDING-Rough-Frame 1/24/2025 Corrections Issued WILLIAM WREN
Green Building Rough 1/24/2025 Not Ready for Inspection WILLIAM WREN
BUILDING-Rough-Frame 1/31/2025 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 1/31/2025 Approved WILLIAM WREN
Green Building Rough 1/31/2025 Approved WILLIAM WREN
Insulation 2/11/2025 Approved WILLIAM WREN
Interior/Exterior Lathing 2/11/2025 Partial Approval WILLIAM WREN
Drywall Nailing 2/26/2025 Approved DAVID ANDERSON
PLUMBING-Rough 2/28/2025 Corrections Issued JACK KARGODORIAN
PLUMBING-Final 3/6/2025 Not Ready for Inspection WILLIAM WREN
Pre-Inspection 3/17/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 3/27/2025 Approved WILLIAM WREN
Final 5/5/2025 Corrections Issued WILLIAM WREN
Green Building Final 5/5/2025 Not Ready for Inspection WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 5/5/2025 SGSOV Approved WILLIAM WREN
Smoke Detectors 5/5/2025 Approved WILLIAM WREN
Final 5/20/2025 OK to Issue CofO WILLIAM WREN
Green Building Final 5/20/2025 Approved WILLIAM WREN