22741 W RUNNYMEDE ST 91307

Certificate Information: 22741 W RUNNYMEDE ST 91307

Application / Permit
24014-20000-01569
Plan Check / Job No.
B24VN05154
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
21'-4" X 13'-6" IRREGULAR SHAPED ADDITION TO EXISTING SINGLE FAMILY DWELLING - PER WFPP
Permit Issued
Issued on 7/17/2024
Issuing Office
Current Status
CofO Corrected on 8/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/18/2024 APPLICANT
Assigned to Plan Check Engineer 4/22/2024 MOHAMMAD ESMAILI
Corrections Issued 4/23/2024 MOHAMMAD ESMAILI
Applicant returned to address corrections 6/13/2024 DANIEL ABRAMYAN
Applicant returned to address corrections 7/1/2024 DANIEL ABRAMYAN
Plan Check Approved 7/8/2024 DANIEL ABRAMYAN
Issued 7/17/2024 APPLICANT
CofO in Progress 8/6/2025 JEFFREY HARTLINE
CofO Issued-Status Void 8/21/2025 JOHN JANSON
Permit Finaled-Status Void 8/21/2025 JOHN JANSON
Re-Activate Permit 8/22/2025 JOHN JANSON
Permit Finaled 8/22/2025 JOHN JANSON
CofO Corrected 8/22/2025 JOHN JANSON
Permit Finaled 8/22/2025 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/14/2024 BRYAN GODINEZ
Roof/Waste drainage to street Cleared 6/14/2024 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 8/14/2024 Partial Approval CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 8/28/2024 Conditional Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 9/27/2024 Approved CHRIS CHRISTENSEN
Reinforced Concrete Frame 9/27/2024 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 1/27/2025 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Rough 1/27/2025 Not Ready for Inspection JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 1/27/2025 Partial Approval JEFFREY HARTLINE
PLUMBING-Rough 1/27/2025 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 2/18/2025 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 2/18/2025 Approved CHRIS CHRISTENSEN
Green Building Rough 2/18/2025 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 2/18/2025 Partial Approval CHRIS CHRISTENSEN
Sewer 2/18/2025 Approved CHRIS CHRISTENSEN
Insulation 2/27/2025 Approved SCOTT SOBEL
Interior/Exterior Lathing 3/12/2025 Partial Approval JEFFREY HARTLINE
Shower Pan 3/12/2025 Approved JEFFREY HARTLINE
Drywall Nailing 4/2/2025 Approved SCOTT SOBEL
Final 7/23/2025 Corrections Issued CHRIS CHRISTENSEN
Footing/Foundation/Slab 7/23/2025 Approved CHRIS CHRISTENSEN
Green Building Final 7/23/2025 Not Ready for Inspection CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 7/23/2025 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 7/23/2025 Approved CHRIS CHRISTENSEN
Final 8/5/2025 OK to Issue CofO JEFFREY HARTLINE
Green Building Final 8/5/2025 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 8/5/2025 SGSOV Approved JEFFREY HARTLINE