22741 W RUNNYMEDE ST 91307
Certificate Information: 22741 W RUNNYMEDE ST 91307
- Application / Permit
- 24014-20000-01569
- Plan Check / Job No.
- B24VN05154
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 21'-4" X 13'-6" IRREGULAR SHAPED ADDITION TO EXISTING SINGLE FAMILY DWELLING - PER WFPP
- Permit Issued
- Issued on 7/17/2024
- Issuing Office
- Current Status
- CofO Corrected on 8/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2024 | MOHAMMAD ESMAILI |
| Corrections Issued | 4/23/2024 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 6/13/2024 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 7/1/2024 | DANIEL ABRAMYAN |
| Plan Check Approved | 7/8/2024 | DANIEL ABRAMYAN |
| Issued | 7/17/2024 | APPLICANT |
| CofO in Progress | 8/6/2025 | JEFFREY HARTLINE |
| CofO Issued-Status Void | 8/21/2025 | JOHN JANSON |
| Permit Finaled-Status Void | 8/21/2025 | JOHN JANSON |
| Re-Activate Permit | 8/22/2025 | JOHN JANSON |
| Permit Finaled | 8/22/2025 | JOHN JANSON |
| CofO Corrected | 8/22/2025 | JOHN JANSON |
| Permit Finaled | 8/22/2025 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2024 | BRYAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 6/14/2024 | BRYAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 8/14/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Deputy Drilled-In Anchors | 8/28/2024 | Conditional Approval | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 9/27/2024 | Approved | CHRIS CHRISTENSEN |
| Reinforced Concrete Frame | 9/27/2024 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 1/27/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 1/27/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2025 | Partial Approval | JEFFREY HARTLINE |
| PLUMBING-Rough | 1/27/2025 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 2/18/2025 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 2/18/2025 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 2/18/2025 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 2/18/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Sewer | 2/18/2025 | Approved | CHRIS CHRISTENSEN |
| Insulation | 2/27/2025 | Approved | SCOTT SOBEL |
| Interior/Exterior Lathing | 3/12/2025 | Partial Approval | JEFFREY HARTLINE |
| Shower Pan | 3/12/2025 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 4/2/2025 | Approved | SCOTT SOBEL |
| Final | 7/23/2025 | Corrections Issued | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 7/23/2025 | Approved | CHRIS CHRISTENSEN |
| Green Building Final | 7/23/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 7/23/2025 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Smoke Detectors | 7/23/2025 | Approved | CHRIS CHRISTENSEN |
| Final | 8/5/2025 | OK to Issue CofO | JEFFREY HARTLINE |
| Green Building Final | 8/5/2025 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 8/5/2025 | SGSOV Approved | JEFFREY HARTLINE |