9900 W LULL ST 91504

Certificate Information: 9900 W LULL ST 91504

Application / Permit
24014-20000-01565
Plan Check / Job No.
B24VN05148
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO EX. SFD FOR NEW PORCH, LIVING ROOM, BATHROOM, AND DINING AREA. REMODEL TO CREATE NEW BEDROOM AND CONVERT EX. BEDROOM TO RECREATION ROOM.
Permit Issued
Issued on 6/10/2024
Issuing Office
Current Status
CofO Issued on 4/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/16/2024 APPLICANT
Assigned to Plan Check Engineer 4/19/2024 SERGIO MUNIZ
Corrections Issued 4/22/2024 SERGIO MUNIZ
Applicant returned to address corrections 5/31/2024 SERGIO MUNIZ
Applicant returned to address corrections 6/6/2024 ROSENDO MEDINA
Plan Check Approved 6/10/2024 ROSENDO MEDINA
Issued 6/10/2024 APPLICANT
CofO in Progress 3/21/2025 DAVID ANDERSON
Permit Finaled 4/8/2025 RUBEN SALAS
CofO Issued 4/8/2025 RUBEN SALAS
Permit Finaled 4/8/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/1/2024 EDGAR ALCARAZ
Sewer availability Cleared 5/1/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 5/2/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/20/2024 Approved DAVID ANDERSON
Deputy Drilled-In Anchors 7/2/2024 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 7/2/2024 Corrections Issued DAVID ANDERSON
Footing/Foundation/Slab 7/5/2024 Approved DAVID ANDERSON
BUILDING-Rough-Frame 7/10/2024 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 7/15/2024 Partial Approval DAVID ANDERSON
Green Building Rough 7/15/2024 Not Ready for Inspection DAVID ANDERSON
Insulation 7/15/2024 Partial Approval DAVID ANDERSON
MERV13>=Rough 7/15/2024 Not Ready for Inspection DAVID ANDERSON
PLUMBING-Rough 7/15/2024 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 7/29/2024 Partial Approval DAVID ANDERSON
HVAC-Rough 7/29/2024 Approved DAVID ANDERSON
Special/Order Compliance 7/29/2024 Corrections Issued DAVID ANDERSON
ELECTRICAL-Rough 8/13/2024 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 8/13/2024 Partial Approval DAVID ANDERSON
BUILDING-Rough-Frame 8/16/2024 Partial Approval DAVID ANDERSON
Green Building Rough 8/16/2024 Approved DAVID ANDERSON
Interior/Exterior Lathing 8/16/2024 Partial Approval DAVID ANDERSON
MERV13>=Rough 8/16/2024 Approved DAVID ANDERSON
PLUMBING-Rough 8/16/2024 Approved DAVID ANDERSON
Insulation 8/21/2024 Not Ready for Inspection DAVID ANDERSON
Shower Pan 8/21/2024 Approved DAVID ANDERSON
Insulation 8/28/2024 Approved DAVID ANDERSON
Drywall Nailing 9/5/2024 Approved DAVID ANDERSON
Interior/Exterior Lathing 10/1/2024 Approved DAVID ANDERSON
BUILDING-Rough-Frame 3/12/2025 Approved DAVID ANDERSON
Final 3/12/2025 Corrections Issued DAVID ANDERSON
Green Building Final 3/12/2025 Approved DAVID ANDERSON
MERV13>=Final 3/12/2025 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 3/12/2025 SGSOV Approved DAVID ANDERSON
Smoke Detectors 3/12/2025 Not Ready for Inspection DAVID ANDERSON
Final 3/18/2025 OK to Issue CofO DAVID ANDERSON
Smoke Detectors 3/18/2025 Approved DAVID ANDERSON