4933-4933 3/4 E MONTE VISTA ST 90042
Certificate Information: 4933-4933 3/4 E MONTE VISTA ST 90042
- Application / Permit
- 24014-20000-01550
- Plan Check / Job No.
- B24VN05094
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ADD 27' X 10' TO & CONVERT THE (E) ATTACHED GARAGE INTO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e), LAUNDRY ROOM, & STORAGE ROOM.
- Permit Issued
- Issued on 5/24/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2024 | ALEC MOUSAKHANIAN |
| Corrections Issued | 4/23/2024 | ALEC MOUSAKHANIAN |
| Building Plans Picked Up | 4/24/2024 | APPLICANT |
| Plan Check Approved | 5/24/2024 | ANGELICA MARTINEZ |
| Issued | 5/24/2024 | APPLICANT |
| CofO in Progress | 4/30/2025 | ALIZAH MAYAGOITIA |
| No Progress | 5/3/2025 | DEROLD HAUFF |
| CofO in Progress | 5/3/2025 | DEROLD HAUFF |
| CofO Issued | 5/7/2025 | DEROLD HAUFF |
| Permit Finaled | 5/7/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/29/2024 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 4/29/2024 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 4/29/2024 | ALEXANDER HELFER |
| Eng Process Fee Ord 176,300 | Cleared | 4/30/2024 | CELINA MORENO |
| Sewer availability | Cleared | 4/30/2024 | CELINA MORENO |
| Specific Plan | Cleared | 5/21/2024 | PABLO ESTRADA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/1/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 8/6/2024 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 8/6/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 10/15/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 11/15/2024 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 12/5/2024 | Corrections Issued | ROY SPAULDING |
| PLUMBING-Rough | 12/5/2024 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 12/11/2024 | Approved | ALIZAH MAYAGOITIA |
| Gas Test | 12/11/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| HVAC-Rough | 12/11/2024 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 12/30/2024 | Corrections Issued | ANTHONY RAMOS |
| Interior/Exterior Lathing | 12/30/2024 | Corrections Issued | ANTHONY RAMOS |
| Interior/Exterior Lathing | 1/10/2025 | Partial Approval | ANTHONY RAMOS |
| Insulation | 1/13/2025 | Partial Approval | ANTHONY RAMOS |
| Drywall Nailing | 1/17/2025 | Approved | ANTHONY RAMOS |
| Insulation | 1/17/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 1/29/2025 | Approved | ALIZAH MAYAGOITIA |
| Shower Pan | 1/29/2025 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 4/3/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 4/14/2025 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 4/14/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 4/14/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 4/14/2025 | SGSOV Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 4/30/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 4/30/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| Green Building Final | 4/30/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 4/30/2025 | Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 4/30/2025 | Approved | ALIZAH MAYAGOITIA |